Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S1W-10010 · Session 1

Further to the answer to question S1W-5884 by Sarah Boyack on 22 June 2000, what carry forward expenditure is budgeted for each of the 49 p…

Answered Asked by Murray Tosh Con Lodged 21 Sep 2000

The question

To ask the Scottish Executive, further to the answer to question S1W-5884 by Sarah Boyack on 22 June 2000, what carry forward expenditure is budgeted for each of the 49 projects for any subsequent years for which figures are available.

The answer

Answered by Sarah Boyack on 20 Oct 2000 · 29 days after it was lodged, 15 days after it was due

Current estimates for expenditure on each of the 49 schemes are as follows:Schemes | 2000-01 | 2001-02 | 2002-03 | 2003-04 | 2004-05
| £ million
A1 Haddington to Dunbar | 0.182 | 10.593 | 21.100 | 5.635 | 0.000
A78 Ardrossan, Saltcoats and Stevenston Bypass | 0.220 | 0.450 | 7.430 | 14.400 | 7.000
A830 Arisaig to Kinsadel | 2.173 | 5.095 | 2.660 | 0.000 | 0.000
A96 Fochabers and Mosstodloch Bypass | 0.242 | 0.210 | 1.450 | 9.000 | 3.000
M77 Malletsheugh to Fenwick | 2.054 | 1.950 | 0.500 | 0.800 | 1.500
A876 Kincardine Bridge Studies |

In the Official Report

No contribution in the Official Report cites S1W-10010 by reference.