Written Question · S1W-09166 · Session 1

On the basis of what costings and timetabling public funding has been allocated to the City of Edinburgh Rapid Transit scheme.

Answered Asked by Kenny MacAskill SNP Lodged 14 Aug 2000

The question

To ask the Scottish Executive on the basis of what costings and timetabling public funding has been allocated to the City of Edinburgh Rapid Transit scheme.

The answer

Answered by Sarah Boyack on 13 Sep 2000 · 30 days after it was lodged, 9 days after it was due

The City of Edinburgh Council submitted its detailed bid for the City of Edinburgh Rapid Transit Scheme to the Transport Challenge Fund competition in June 1996. That bid contained estimated costs of and a projected timescale for development. The then Government gave the council permission to incur expenditure of up to £15 million under section 94 of the Local Government (Scotland) Act 1973, with this award timetabled as follows:1997-98 | 1998-99 | 1999-2000
£4 million | £6 million | £5 million
At the council's request, the award was subsequently reprofiled to accommodate slippage caused by the parliamentary Order and the development of the Private Finance Initiative package. Further re-profiling of the award may be necessary.