SPCB Written Question · S1W-08962 · Session 1
What capital contracts are currently out to tender, or being prepared for tender, in relation to the Holyrood Project, indicating in each c…
The question
To ask the Presiding Officer what capital contracts are currently out to tender, or being prepared for tender, in relation to the Holyrood Project, indicating in each case the timescale for award of the contract, commencement on site, and completion of works.
The answer
The information is as follows:Works Package | Estimated Award | Estimated Site Start | EstimatedCompletion
QH Demolition & Reconstruction | 25/08/00 | 04/09/00 | 25/06/01
Lifts | 31/08/00 | 19/02/01 | 19/05/01
MSP Roofing | 01/09/00 | 08/01/01 | 30/04/01
Substructure Concrete EastBasement | 01/09/00 | 11/09/00 | 20/11/00
MSP Cladding | 29/09/00 | 12/02/01 | 12/06/01
Mechanical &Plumbing West | 29/09/00 | 12/02/01 | 29/07/02
Electrical WorksWest | 13/10/00 | 19/03/01 | 19/06/01
MSP Carpentry &Joinery | 13/10/00 | 02/04/01 | 03/12/01
QH ExternalRender | 10/11/00 | 12/03/01 | 06/05/02
QH Demolition & Reconstruction | 25/08/00 | 04/09/00 | 25/06/01
Lifts | 31/08/00 | 19/02/01 | 19/05/01
MSP Roofing | 01/09/00 | 08/01/01 | 30/04/01
Substructure Concrete EastBasement | 01/09/00 | 11/09/00 | 20/11/00
MSP Cladding | 29/09/00 | 12/02/01 | 12/06/01
Mechanical &Plumbing West | 29/09/00 | 12/02/01 | 29/07/02
Electrical WorksWest | 13/10/00 | 19/03/01 | 19/06/01
MSP Carpentry &Joinery | 13/10/00 | 02/04/01 | 03/12/01
QH ExternalRender | 10/11/00 | 12/03/01 | 06/05/02