SPCB Written Question · S1W-08961 · Session 1
What capital contracts have been let so far in relation to the Holyrood Project, indicating in each case the timescale for the contract, th…
The question
To ask the Presiding Officer what capital contracts have been let so far in relation to the Holyrood Project, indicating in each case the timescale for the contract, the name of the successful contractor and the total cost of the contract.
The answer
The contract sums involved are commercially confidential. In line with standard public sector procurement policy the financial details of the successful tender are commercially confidential, as disclosure of such information could substantially prejudice the Company's future competitive position. The rest of the information is as follows:Works Package | Contractor | Contract Let | Duration
Retention West Basement | Amec Civil Engineering Ltd | 19/04/99 | 4 months
Excavation West | Barr Ltd | 19/07/99 | 3 months
Well Probing | Wimtec Environmental Ltd | 22/07/99 | 11 months
Piling West Basement | Amec Civil Engineering Ltd | 13/09/99 | 3 months
Substructure West Basement | O'Rourke Civil Engineering Ltd | 12/10/99 | 5 months
Tower Cranes | Select Plant Hire Ltd | 06/11/99 | 20 months
Asbestos/Pigeon Dropping Removal | Chamic Industrial Services Ltd | 29/11/99 | 5 months
Well Drilling | Richies Ltd | 13/12/99 | 5 months
QH Scaffolding | Lyndon Scaffolding PLC | 29/02/00 | 19 months
MSP Frame | O'Rourke Civil Engineering Ltd | 10/04/00 | 10 months
Electrical Enabling works | James Scott Ltd | 08/05/00 | 10 months
Retention West Basement | Amec Civil Engineering Ltd | 19/04/99 | 4 months
Excavation West | Barr Ltd | 19/07/99 | 3 months
Well Probing | Wimtec Environmental Ltd | 22/07/99 | 11 months
Piling West Basement | Amec Civil Engineering Ltd | 13/09/99 | 3 months
Substructure West Basement | O'Rourke Civil Engineering Ltd | 12/10/99 | 5 months
Tower Cranes | Select Plant Hire Ltd | 06/11/99 | 20 months
Asbestos/Pigeon Dropping Removal | Chamic Industrial Services Ltd | 29/11/99 | 5 months
Well Drilling | Richies Ltd | 13/12/99 | 5 months
QH Scaffolding | Lyndon Scaffolding PLC | 29/02/00 | 19 months
MSP Frame | O'Rourke Civil Engineering Ltd | 10/04/00 | 10 months
Electrical Enabling works | James Scott Ltd | 08/05/00 | 10 months
In the Official Report