Further to the answer to question S1W-4256 by Sarah Boyack on 27 April 2000, whether it is now in a position to state the timescale for com…

Answered Asked by Murray Tosh Con Lodged 21 Jul 2000

The question

To ask the Scottish Executive, further to the answer to question S1W-4256 by Sarah Boyack on 27 April 2000, whether it is now in a position to state the timescale for completion of multi-modal studies on the M8 and M80 corridors.

The answer

Answered by Sarah Boyack on 10 Aug 2000 · 20 days after it was lodged, on time

The scoping report for the Central Scotland multi-modal studies confirms my earlier estimate that the work programme will take 18 months to complete, reporting in early 2002. This timescale is consistent with similar multi-modal studies currently being undertaken in England.

In the Official Report

No contribution in the Official Report cites S1W-08808 by reference.