Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S1W-08553 · Session 1

When the last safety audit was carried out on the A725 and which parts of the route were covered by it.

Answered Asked by Linda Fabiani SNP Lodged 5 Jul 2000

The question

To ask the Scottish Executive when the last safety audit was carried out on the A725 and which parts of the route were covered by it.

The answer

Answered by Sarah Boyack on 19 Jul 2000 · 14 days after it was lodged, on time

Safety audits are only undertaken when road improvements are constructed. However, a Route Accident Reduction Plan (RARP) study was carried out in 1999 on the A725 trunk road between Whirlies Roundabout, East Kilbride and Whistleberry Toll, Bothwell.A RARP study is currently ongoing on the A725 between Raith Interchange and Shawhead Junction with the A8.

In the Official Report

No contribution in the Official Report cites S1W-08553 by reference.