Written Question · S1W-08553 · Session 1
When the last safety audit was carried out on the A725 and which parts of the route were covered by it.
The question
To ask the Scottish Executive when the last safety audit was carried out on the A725 and which parts of the route were covered by it.
The answer
Safety audits are only undertaken when road improvements are constructed. However, a Route Accident Reduction Plan (RARP) study was carried out in 1999 on the A725 trunk road between Whirlies Roundabout, East Kilbride and Whistleberry Toll, Bothwell.A RARP study is currently ongoing on the A725 between Raith Interchange and Shawhead Junction with the A8.
In the Official Report
No contribution in the Official Report cites S1W-08553 by reference.