Parliament Workbench
Data: Motions & questions to 19 Nov 2026

Written Question · S1W-08356 · Session 1

Whether it has recovered in full the costs of the repairs to the Erskine Bridge, following the damage caused by an offshore structure, from…

Answered Asked by Trish Godman Lab Lodged 29 Jun 2000

The question

To ask the Scottish Executive whether it has recovered in full the costs of the repairs to the Erskine Bridge, following the damage caused by an offshore structure, from the parties deemed to be negligent.

The answer

Answered by Sarah Boyack on 13 Jul 2000 · 14 days after it was lodged, on time

The Scottish Executive is committed to recovering the costs of the repairs to the Erskine Bridge. Counsel has been instructed with a view to raising court proceedings against those considered to be responsible.

In the Official Report

No contribution in the Official Report cites S1W-08356 by reference.