The question

To ask the Scottish Executive how much public money was spent in providing the facilities, infrastructure and incentives to encourage Canon to locate in Glenrothes.

The answer

Answered by Henry McLeish on 28 Jun 2000 · 14 days after it was lodged, on time

In October 1994 Canon was offered RSA of £530,000 which was paid in full.In February 1996 Canon was offered £3,000,000 which was reduced to £2,530,435 in January 1999 and a total of £1,500,000 was paid.Officials in the Monitoring department, Scottish Executive, are in touch with the company concerning RSA clawback.