The question
To ask the Presiding Officer by what date the Scottish Parliamentary Corporate Body expects to make available to the Parliament details of how the building, fit out and other costs of the Holyrood Project will be reduced in order to meet the agreed #195 million budget.
The answer
SPCB Report No 4 of 30 March 2000 to MSPs made clear that, based on the latest design proposals, the project can be delivered for £195 million. The Quantity Surveyor's "Stage D" cost report for June 2000 is consistent with that figure. The Holyrood Progress Group would advise MSPs if there were any change to that position.
In the Official Report
No contribution in the Official Report cites S1W-07834 by reference.