What powers local authorities have to ensure property developers do not prolong or do not finish developments, and what action it plans to …

Answered Asked by Shona Robison SNP Lodged 6 Jun 2000

The question

To ask the Scottish Executive what powers local authorities have to ensure property developers do not prolong or do not finish developments, and what action it plans to take to strengthen local authorities' powers to deal with such situations.

The answer

Answered by Sarah Boyack on 20 Jun 2000 · 14 days after it was lodged, on time

Section 58 of the Town and Country Planning (Scotland) Act 1997 provides that development to which a planning permission relates must be begun within five years of the date on which the permission was granted unless the permission stipulates a different period.Section 61 of the Act provides that, if after the expiry of the five year (or other) period a planning authority is of the opinion that the development will not be completed within a reasonable period it may serve a completion notice stating that the planning permission will cease to have effect at the expiration of a period (not less than 12 months) specified in the notice. Such a notice has no effect unless it is confirmed by the Scottish Ministers.Planning authorities also have powers under section 65 of the Act to revoke or modify planning permission. Where the permission relates to the carrying out of building or other operations these powers may be exercised at any time before those operations have been completed; and where the permission relates to the change of use of any land, at any time before the change has taken place. In exercising these powers authorities may be liable to claims for compensation in terms of section 76 of the Act.Should a building or site become unsafe, there are powers under the Building (Scotland) Act 1959 to require a developer to make them safe.The Executive has no plans to amend the planning provisions and, although the building control system is under review, there are no plans at present to extend the relevant powers.

In the Official Report

No contribution in the Official Report cites S1W-07708 by reference.