Further to the answers to questions S1W-6991 and S1W-6992 by Sarah Boyack on 1 June 2000, what the timescale will be for the introduction o…

Answered Asked by Murray Tosh Con Lodged 2 Jun 2000

The question

To ask the Scottish Executive, further to the answers to questions S1W-6991 and S1W-6992 by Sarah Boyack on 1 June 2000, what the timescale will be for the introduction of secondary legislation, in the form of an amendment to the Town and Country Planning (General Permitted Development) (Scotland) Order 1992, to remove permitted development rights in general for telecommunications developments.

The answer

Answered by Sarah Boyack on 21 Jun 2000 · 19 days after it was lodged, 5 days after it was due

We are currently discussing the future scope of planning controls over telecommunications with local authorities and the industry in the light of the recommendations in the report from the Transport and the Environment Committee. We intend consulting on draft legislation and associated guidance during the summer. Our normal practice is to allow eight weeks for responses. We will give full consideration to the responses and bring forward the necessary legislation as soon as possible thereafter.

In the Official Report