Written Question · S1W-07181 · Session 1
Further to the answer to question S1W-2877 by Sarah Boyack on 12 January 2000, whether it will clarify what Scottish Enterprise's delegated…
The question
To ask the Scottish Executive, further to the answer to question S1W-2877 by Sarah Boyack on 12 January 2000, whether it will clarify what Scottish Enterprise's delegated authority is and whether the spending category indicated would be allowable within the figure for delegated authority.
The answer
Scottish Enterprise does not propose to make a direct contribution to the cost of completion of the M74. However Scottish Enterprise is committed to co-operating with the local authorities concerned to explore the economic development opportunities which will be created by the completion of the M74. It is too early to say what form any involvement by Scottish Enterprise might take in economic development activities associated with the extension of the M74 or to identify the appropriate level of delegated authority.
In the Official Report
No contribution in the Official Report cites S1W-07181 by reference.