SPCB Written Question · S1W-06521 · Session 1
Further to his answer to question S1W-5938 on 6 April 2000, what the current base works cost estimate is for the Holyrood Project; when thi…
The question
To ask the Presiding Officer, further to his answer to question S1W-5938 on 6 April 2000, what the current base works cost estimate is for the Holyrood Project; when this figure was last contractually altered for the purpose of calculating the fees of the design team; what the dates were of any previous alteration to this figure, and on whose authority any previous alterations to this figure were made.
The answer
The current base works cost estimate for the Holyrood Project is £108 million. This figure was agreed by Parliament following the Holyrood Project debate on 5 April 2000. The previous base works cost estimate was £62 million and was also agreed by Parliament following the first Holyrood Project debate on 17 June 1999. The Design Team fees will be adjusted in line with the latest change.
In the Official Report
No contribution in the Official Report cites S1W-06521 by reference.