What is (a) the total value of the contracts awarded to date in respect of the Holyrood project, (b) the percentage of the total value that…

Answered Asked by Linda Fabiani SNP Lodged 3 Apr 2000

The question

To ask the Presiding Officer what is (a) the total value of the contracts awarded to date in respect of the Holyrood project, (b) the percentage of the total value that related to prime costs, provisional sums and contingency, and (c) the estimated value of those contracts at completion.

The answer

Answered by David Steel on 5 Apr 2000 · 2 days after it was lodged, on time

The information is as follows:The total value of works packages awarded to date is £13.5 million.The level of provision sums is on average 2%. The project cost estimate contains an overall contingency allowance which is not allocated to individual works packages.
The estimated final value of the works packages awarded to date is £15 million.
These costs exclude site purchase, demolition, archaeology, design team fees and VAT.