SPCB Written Question · S1W-05937 · Session 1
What is (a) the total value of the contracts awarded to date in respect of the Holyrood project, (b) the percentage of the total value that…
The question
To ask the Presiding Officer what is (a) the total value of the contracts awarded to date in respect of the Holyrood project, (b) the percentage of the total value that related to prime costs, provisional sums and contingency, and (c) the estimated value of those contracts at completion.
The answer
The information is as follows:The total value of works packages awarded to date is £13.5 million.The level of provision sums is on average 2%. The project cost estimate contains an overall contingency allowance which is not allocated to individual works packages.
The estimated final value of the works packages awarded to date is £15 million.
These costs exclude site purchase, demolition, archaeology, design team fees and VAT.
The estimated final value of the works packages awarded to date is £15 million.
These costs exclude site purchase, demolition, archaeology, design team fees and VAT.
In the Official Report
No contribution in the Official Report cites S1W-05937 by reference.