By how many weeks the making of concrete moulds and pouring of concrete foundations in the Holyrood Project are behind schedule.

Answered Asked by Margo MacDonald SNP Lodged 4 Feb 2000

The question

To ask the Presiding Officer by how many weeks the making of concrete moulds and pouring of concrete foundations in the Holyrood Project are behind schedule.

The answer

Answered by David Steel on 16 Feb 2000 · 12 days after it was lodged, on time

The work package, which includes the fabrication of concrete moulds and pouring of concrete foundations, is 12 weeks in delay. This is primarily to prevent nugatory expenditure while the feasibility of meeting the Parliament's extra accommodation requirements is being investigated.