By how many weeks the making of concrete moulds and pouring of concrete foundations in the Holyrood Project are behind schedule.
The question
To ask the Presiding Officer by how many weeks the making of concrete moulds and pouring of concrete foundations in the Holyrood Project are behind schedule.
The answer
The work package, which includes the fabrication of concrete moulds and pouring of concrete foundations, is 12 weeks in delay. This is primarily to prevent nugatory expenditure while the feasibility of meeting the Parliament's extra accommodation requirements is being investigated.