Written Question · S1W-04009 · Session 1
Further to the answer to question S1W-2858 by Sarah Boyack on 12 January 2000, when and by whom the decision to abandon the Crossrail proje…
The question
To ask the Scottish Executive, further to the answer to question S1W-2858 by Sarah Boyack on 12 January 2000, when and by whom the decision to abandon the Crossrail project was made; whether it made a unilateral decision to withdraw its support from Crossrail, and whether it has advised the promoters of Crossrail, including Strathclyde Passenger Transport Executive, of its decision.
The answer
I can confirm that a feasibility study on Glasgow Cross Rail was completed in 1995 by Railtrack on behalf of Strathclyde Passenger Transport Authority. I understand it is still being evaluated by the authority. The Scottish Executive has made no unilateral decision to withdraw its support from the project since its support has never been sought.
In the Official Report
No contribution in the Official Report cites S1W-04009 by reference.