Written Question · S1W-03678 · Session 1
Further to the answer to question S1W-3423 by Sarah Boyack on 16 December 1999, whether this answer confirms that the entire final costs of…
The question
To ask the Scottish Executive, further to the answer to question S1W-3423 by Sarah Boyack on 16 December 1999, whether this answer confirms that the entire final costs of the proposed Public Private Partnerships for the M77 Fenwick to Malletsheugh motorway extension will be paid for from the Scottish Consolidated Fund.
The answer
A Public Private Partnership approach to the procurement of the M77 between Fenwick and Malletsheugh will be pursued provided that this approach demonstrates value for money. The entire costs of the procurement would then be paid from the Scottish Consolidated Fund.
In the Official Report
No contribution in the Official Report cites S1W-03678 by reference.