Whether all of the land required for the projected M77 extension from Malletsheugh to Fenwick has been acquired, whether any land is curren…

Answered Asked by Murray Tosh Con Lodged 10 Dec 1999

The question

To ask the Scottish Executive whether all of the land required for the projected M77 extension from Malletsheugh to Fenwick has been acquired, whether any land is currently subjected to compulsory purchase or whether any land is being acquired by negotiations, subject to conditions, including time delays in acquisition.

The answer

Answered by Sarah Boyack on 13 Jan 2000 · 34 days after it was lodged, 20 days after it was due

The land for the M77 extension between Fenwick and Malletsheugh has not yet been purchased. Three Compulsory Purchase Orders to acquire most of the land for the scheme were made at the end of last year. Subject to the satisfactory completion of the statutory procedures, ownership of this land will be vested in Scottish Ministers in spring 2000. Additional plots of land for various additional drainage, landscaping and access works are being acquired by negotiation.