Written Question · S1W-02875 · Session 1
Whether it will project a target date for completing work on the 91 bridges identified in Travel Choices for Scotland.
The question
To ask the Scottish Executive whether it will project a target date for completing work on the 91 bridges identified in Travel Choices for Scotland.
The answer
A programme to reassess 58 of the 91 bridges that failed the first level assessment is in progress. To date 18 structures have been redetermined as adequate with 20 confirmed failures. Reassessment of the remainder is expected to be complete by the middle of next year. Until then we cannot give a target date for completing the strengthening and replacement of sub-standard bridges.
In the Official Report