Further to the answer to question S1W-1791 by Ms Wendy Alexander on 26 October 1999, what the reasons were for late decisions on ESF Object…

Answered Asked by Michael Matheson SNP Lodged 28 Oct 1999

The question

To ask the Scottish Executive, further to the answer to question S1W-1791 by Ms Wendy Alexander on 26 October 1999, what the reasons were for late decisions on ESF Objective 3 Grants.

The answer

Answered by Jack McConnell on 17 Jan 2000 · 81 days after it was lodged, 67 days after it was due

I understand that the decisions on ESF Objective 3 grants for 1998 were delayed because of a changeover of administrative procedures. In order to prevent the adverse effects of these delays on small organisations in the voluntary sector which had become dependent upon continued ESF funding, it was agreed to provide the relatively modest funding under section 10 of the Social Work (Scotland) Act 1968 to which the earlier reply referred.

In the Official Report

No contribution in the Official Report cites S1W-02229 by reference.