Parliament Workbench
Data: Motions & questions to 19 Nov 2026

Written Question · S1W-01417 · Session 1

What works are programmed for the Kingston Bridge on the M8, what plans it has to repair the bridge, and when it expects the bridge to be r…

Answered Asked by Murray Tosh Con Lodged 7 Sep 1999

The question

To ask the Scottish Executive what works are programmed for the Kingston Bridge on the M8, what plans it has to repair the bridge, and when it expects the bridge to be restored to full operation.

The answer

Answered by Sarah Boyack on 27 Sep 1999 · 20 days after it was lodged, on time

A major contract to address Kingston Bridge's structural problems is in progress. The works include strengthening of the centre and side spans of the deck, demolition and reconstruction of the main supports, and restoring the articulation of the bridge. This contract is expected to be completed in autumn 2000.Further works to improve the approach viaducts and ramps are planned. These works will take a number of years to complete depending on the availability of funds.Until the programme for the remaining works has been finalised we cannot say when the current traffic restrictions will be removed and the bridge restored to full operation.

In the Official Report

No contribution in the Official Report cites S1W-01417 by reference.