SPCB Written Question · S1W-00232 · Session 1

Whether he will list the numbers and categories of staff to be accommodated in the new parliament building under the #50 million cost plan …

Answered Asked by Linda Fabiani SNP Lodged 24 Jun 1999

The question

To ask the Presiding Officer whether he will list the numbers and categories of staff to be accommodated in the new parliament building under the #50 million cost plan and the revised #62 million cost plan.

The answer

Answered by David Steel on 7 Jul 1999 · 13 days after it was lodged, on time

The information requested is given in the table.Staff/Worker Category(1) | Original Brief(£50m)(2) | Revised Brief(£62m)(2)
MSPs + MSPs' researcher/secretary(3) | 258 | 258
Clerks, Administrative staff, Executive staff assigned to Ministers(4) | 153 | 260
Facilities and Security(5)Management and contracted service providers | 302 | 290
(1)Staffing estimates for facilities management and security based on anticipated requirements (November 1998) at Holyrood. Clerks and other administrative staff as estimated at March 1999.(2)Excludes VAT, fees, contingencies, etc.(3)Allows one space per MSP for researcher/secretary.(4)Includes parliamentary clerks and administrative staff (excluding facilities and security management) and Executive staff assigned to Ministers who will use the building as necessary.(5)Includes parliamentary facilities and security management and possible contracted service providers eg mailroom, catering and day cleaners. Includes part-time staff.