An Energy Strategy for Scotland

Carried Lodged by Murdo Fraser Con Lodged 23 Feb 2015 Debate 25 Feb 2015

The motion

That the Parliament notes with concern the latest threats to the continued operation of Longannet Power Station in Fife, contributing 25% of Scotland’s electricity output at its peak; urges Scottish Power and National Grid to work toward a resolution of the transmission charging issue, but recognises that EU emissions rules and carbon pricing mean that the future of Longannet beyond 2020 is very uncertain; further notes that Scotland’s two nuclear power stations, at Torness and Hunterston, which produced 35% of Scotland’s electricity output between them in 2013, are due to close by 2025; acknowledges the significant loss of electricity generating capacity that this is likely to cause in the next decade; notes that renewable energy, while having a part to play in the energy mix, cannot supply baseload from intermittent sources and that the Scottish Government is opposed to any new nuclear stations being built, and calls on the Scottish Government to bring forward as a matter of urgency a new energy strategy, setting out how new generating capacity will be created to ensure that the lights are kept on without Scotland having to rely on importing energy from the rest of the UK.

What MSPs voted on: the motion as amended

The Conservatives’ motion was rewritten by an SNP amendment (S4M-12395.1) before this vote. A vote ‘for’ was a vote for the SNP’s wording.

That the Parliament notes with concern the latest threats to the continued operation of Longannet Power Station in Fife,
175 words removed by S4M-12395.1contributing 25% of Scotland’s electricity output at its peak; urges Scottish Power and National Grid to work toward a resolution of the transmission charging issue, but recognises that EU emissions rules and carbon pricing mean that the future of Longannet beyond 2020 is very uncertain; further notes that Scotland’s two nuclear power stations, at Torness and Hunterston, which produced 35% of Scotland’s electricity output between them in 2013, are due to close by 2025; acknowledges the significant loss of electricity generating capacity that this is likely to cause in the next decade; notes that renewable energy, while having a part to play in the energy mix, cannot supply baseload from intermittent sources and that the Scottish Government is opposed to any new nuclear stations being built, and calls on the Scottish Government to bring forward as a matter of urgency a new energy strategy, setting out how new generating capacity will be created to ensure that the lights are kept on without Scotland having to rely on importing energy from the rest of the UK.
S4M-12395.1 SNP brought about by the UK’s discriminatory transmission charging regime; further notes that cleaner thermal generation progressively fitted with carbon capture and storage technology will continue to play an important role in securing Scotland’s future energy mix, alongside the expansion of renewables, as set out in the Scottish Government’s Electricity Generation Policy Statement 2013; recognises that UK energy policy and regulation actively discourages the construction of new conventional thermal generating plants in Scotland compared with other locations in the UK, given the higher transmission charges faced by Scottish generators; shares the Scottish Government’s disappointment at the further delay in implementing transmission pricing reforms stemming from Ofgem’s Project TransmiT; recognises the significant progress in renewables deployment in Scotland, with over 44% of gross electricity consumption met from renewable sources in 2013; supports the need for increased investment in large-scale flexible electricity storage solutions, including pumped storage, to complement the increasing deployment of renewable technologies, and further supports the First Minister’s call for the UK Government to undertake a dedicated electricity capacity assessment for Scotland and to transfer to the Scottish Parliament the authority to set a Scottish security and quality of supply standard for electricity.

Final wording as read into the Official Report at Decision Time. The marked changes are worked out by this site from the amendment texts and match that wording.

Amendments

  1. S4M-12395.1 SNP Fergus Ewing Agreed vote, 61–53
  2. S4M-12395.3 Labour Lewis Macdonald Fell per the Official Report
  3. S4M-12395.2 Green Patrick Harvie Defeated vote, 5–79

Vote

1 division
  1. 25 Feb 2015
    An Energy Strategy for Scotland
    S4M-12395as amended by SNP
    Carried
    61 for, 53 against

Amendments

3
  1. Carried
    61 for, 53 against
  2. Defeated
    5 for, 79 against
  3. No recorded vote

Supporters

No MSP has added their name to this motion.

In the Official Report

4 contributions mention S4M-12395
  1. 25 Feb 2015
    Energy Strategy
    John Scott Con Meeting of the Parliament

    The next item of business is a debate on motion S4M-12395, in the name of Murdo Fraser, on an energy strategy for Scotland. I call Murdo Fraser to speak to and move the motion. 14:41

  2. 25 Feb 2015
    Decision Time
    Tricia Marwick Meeting of the Parliament

    There are seven questions to be put as a result of today’s business. I remind members that, in relation to the debate on an energy strategy for Scotland, if the amendment in the name of Fergus Ewing is agreed to, the amendment in the name …

  3. 25 Feb 2015
    Decision Time
    Tricia Marwick Meeting of the Parliament

    The amendment in the name of Lewis Macdonald therefore falls. The next question is, that amendment S4M-12395.2, in the name of Patrick Harvie, which seeks to amend motion S4M-12395, in the name of Murdo Fraser, on an energy strategy for Sc…

  4. 25 Feb 2015
    Decision Time
    Tricia Marwick Meeting of the Parliament

    The next question is, that motion S4M-12395, in the name of Murdo Fraser, on an energy strategy for Scotland, as amended, be agreed to. Are we agreed? Members: No.