I have a few minor questions, some of which are on issues that we have already covered to some extent.
The Edinburgh Evening News recently reported that “construction chiefs”—I suppose that that is what the witnesses are—thought that the project might come in under budget and ahead of schedule. Do the figures that the witnesses gave us cover the latest budget estimate and take into account that speculation?
I am aware that as we get towards the end of the project the scope for the figure to change becomes limited. Is the figure that you gave us most likely to be the final re-estimate of construction costs?
The speculation also suggested that the bridge might be completed ahead of schedule. Notwithstanding the fact that the convener has already had a go at you to see whether he could get an opening date, is the project proceeding on schedule and is there now only limited scope for it to be significantly shortened?
I listen to the news, and in late November last year the BBC reported that Carlo Germani would leave the project in December and that a new project director would be appointed. Has that happened? Can you give an assurance that the change has had little or no impact on the project?
Going back to the structure of the bridge and its future management, I want to raise the issue of lighting, for a number of reasons. I presume that, for marine navigation purposes, the feet of the towers are already lit during the hours of darkness. Is that the case?
I notice that there are already warning lights on the tops of the towers. They will, of course, go up as the towers go up. What are the plans for illuminating the tops of the towers or marking them with lights after construction is completed? Are there likely to be any issues for the local population with regard to the presence of the lights?
You mentioned aesthetic lighting. The Forth rail bridge has been illuminated for some time. If you are to use aesthetic lighting on the new bridge, have you taken into account the overall appearance of the area during the hours of darkness and how the lighting on one bridge can complement that on the others?
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.