Edinburgh to Glasgow Improvement Programme

Portfolio Question Time Infrastructure, Investment and Cities

Wednesday 5 February 2014 Meeting of the Parliament Questions 6 contributions · 3 speakers Watch on Scottish Parliament TV

Speakers

Choose an MSP to read only their contributions

The record

6 contributions
Annabel Goldie Con West Scotland
link


5. To ask the Scottish Government, in light of the recently announced £90 million in additional costs, whether it plans further upgrades to the Glasgow to Edinburgh rail link under the current improvement plan. (S4O-02871)

Keith Brown SNP The Minister for Transport and Veterans · Clackmannanshire and Dunblane
link
Cost increases in the final business case incorporate more ambitious plans around the redevelopment of Queen Street than originally planned. Although no further upgrades are planned during the first phase, which I announced in July 2012, remaining elements of the Edinburgh to Glasgow improvement programme will be delivered in future phases.

Annabel Goldie Con West Scotland
link
The Scottish National Party’s 2011 manifesto beguiled us with journey times of just over 30 minutes between Glasgow and Edinburgh. Now we are told to forget that and accept that we might get journey times of 42 minutes in five years’ time. Bigger trains and longer platforms may address a capacity issue, but what I and the many other regular commuters on that route want now are quicker trains and shorter journeys. When will the minister even partly deliver on his manifesto promise?

Keith Brown SNP The Minister for Transport and Veterans · Clackmannanshire and Dunblane
link
I have laid out exactly when we will do that, with the publication of the final business case. I made the point in my original answer and will make it again that this is the first phase of the Edinburgh to Glasgow improvement programme and there is more to come. We have also said that, after we have electrified the Edinburgh to Glasgow line, we will start to electrify around 100km of the remaining track in Scotland every year. That is a substantial commitment.

Although it is important to emphasise the extent to which Glasgow and Edinburgh will benefit from the project—there are already four lines there, and there is the possibility of high-speed rail between Edinburgh and Glasgow—it is also important to concentrate on the benefits for other parts of the network. We will continue to do that, and further phases of EGIP will take place.

Given the constraints that we have on the budget, this is an excellent project that ensures that we spend our resources properly. We have a good track record on delivering major initiatives, such as the Airdrie to Bathgate project and the M74 project. However, we do so in the context of the resources that we have.

Mark Griffin Lab Central Scotland
link
When will passengers in central Scotland benefit from those journey-time reductions and service improvements? The minister has repeatedly stated that phase 2 will go ahead, but his business case states that ministers will not take a decision until a later date.

Keith Brown SNP The Minister for Transport and Veterans · Clackmannanshire and Dunblane
link
Of course, the initial benefit will be to reduce the journey time to 42 minutes. In the original case, the target was not just over 30 minutes, which Annabel Goldie suggested it was, but 37 minutes. The major reduction to 42 minutes represents a reduction of around 20 per cent in the time that it takes to travel between Edinburgh and Glasgow. That is in the first phase. Further phases will come after that. Of course, that decision is one to be taken as time and resources allow.

To me, that is a substantial improvement in terms of capacity, the efficiency of the railway and the environmental impact of the railway, as it is electric rather than diesel. Those huge benefits will happen in the early stage. I think that many people travelling regularly between Glasgow and Edinburgh will be grateful for that initial journey-time reduction, and for the additional capacity on the line.

Motions, questions and votes

Linked from this item of the Official Report
  1. Infrastructure, Investment and Cities Questions · 1
  2. Edinburgh to Glasgow Improvement Programme (Business Case) Questions · 6
  3. Edinburgh to Glasgow Improvement Programme (Business Case) Questions · 7
  4. East Coast Railway Line (Upgrading Cost) Questions · 4
  5. Edinburgh to Glasgow Improvement Programme Questions · 6
  6. Mobile Phone Coverage Questions · 4
  7. Transport Scotland (Trunk Road Closures) Questions · 4
  8. Glasgow Prestwick Airport Questions · 6
  9. Creative Scotland (Youth Music Initiative) Questions · 4
  10. Independence (Overseas Properties) Questions · 4
  11. Independence (Overseas Representation) Questions · 8
  12. Historic Locations and Events (Promotion) Questions · 4
  13. Independence (Inward Investment in Film and Television) Questions · 4
  14. British Embassies (Scotland’s Interests) Questions · 6
  15. National Libraries Day Questions · 4
  16. UNESCO World Heritage Sites Questions · 4
  17. International Strategy (Priorities) Questions · 4
  18. Budget (Scotland) (No 3) Bill: Stage 3 Bill debate · 105
  19. Business Motions Business motions · 2
  20. Decision Time Decision time · 7
  21. Female Genital Mutilation Members’ business · 23

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.