Yes. Thank you, convener. I have come fresh from the launch of Bannockburn live, which is going to be a terrific success, as I know we all wish it to be. Thank you for the invitation to be here this morning.The renewables obligation or RO drives investment in renewable electricity capacity across the country. Since its introduction in 2002, renewable electricity capacity across Scotland has almost quadrupled. Indeed, the final figures for 2012 show that renewable generation accounted for an equivalent 40 per cent of gross Scottish electricity demand, putting us well on our way to achieving our interim target of 50 per cent by 2015. We need to ensure that the upward trend continues. We want to see more generation coming from offshore wind, wave and tidal energy—sources in which Scotland has a huge competitive advantage and can create world-leading industries. Of course, the renewables obligation mechanism is due to be replaced by a new system of support based on a contract for difference. I will come on to talk about that later.The amendments in the draft order are designed to ensure that the RO legislation remains fit for purpose and that we continue to attract investment in new technologies and developments across Scotland in a way that is both cost effective and sustainable. As is customary, we have proposed the same amendments, generally, as will apply across the rest of the United Kingdom. That approach is favoured by a majority and is fundamental to the successful and effective operation of the mechanism. However, as has been the case on previous occasions, there are some important exceptions to that approach.The most prominent exception is our decision to introduce two new bands to provide additional support for innovative offshore wind generation from, first, test and demonstration centres and, secondly, pilot projects that comprise non-fixed or floating turbines. Those new and higher bands are explicitly limited to apply to offshore wind turbines that are innovative and new to the marketplace. They are aimed at reducing the costs of generation from such sources, enabling them to make a greater contribution to meeting our binding European Union targets.We have already seen a commitment from Statoil to develop its Hywind pilot project off the coast of Peterhead. The Crown Estate’s leasing round for floating offshore wind will conclude in the coming weeks, and we hope that a number of other developers will secure exclusivity rights to pursue developments in Scottish waters and bring economic benefit to these shores.The new offshore bands have been introduced and costed on the basis of the capacity that we expect to come forward between now and the order’s closure in 2017. However, there are no limits or thresholds within the provisions.The remaining changes that are set out in our amending order mirror the changes that are being made to the other UK obligation mechanisms. The first of them relates to tighter biomass sustainability criteria. The committee might remember from last year, when we introduced a 15MW cap on biomass, that we were considering the introduction of tighter sustainability standards under the RO. The amendment order introduces those changes, which are designed to ensure that biomass material is sourced responsibly and in a way that minimises or eliminates adverse impacts.The order amends the information that is to be provided, on a per consignment basis, to the Office of Gas and Electricity Markets—Ofgem—by all stations over 50kW that use solid biomass and/or biogas. That includes the introduction of a timber standard, which is focused on sourcing wood from legal and sustainable sources, and a tighter greenhouse gas threshold for dedicated biomass stations that were accredited after 1 April 2013. It also creates a new requirement for generating stations of 1MW and above to provide an independent sustainability audit report for solid and gaseous biomass, which will report against greenhouse gases, land criteria and the timber standard.Those reporting and audit requirements will enable generators to become familiar with the sustainability criteria before the introduction of the further amendments that will be made next year to make compliance with the sustainability criteria mandatory for generating stations of 1MW and above. The order also refers to the latest combined heat and power quality assurance standard, which has been tightened to reflect improvements in the efficiency of such schemes.As the committee knows, the RO mechanism is due to be replaced by a new system of financial support that is based on contracts for difference. The process of reforming the UK electricity market seems to have been running for as long as most of us can remember, but there are still important decisions to be made. We have expressed concerns that the design and limits of the contract for difference mechanism will restrict the opportunities to develop the renewables industry in Scotland and that, as a result, we risk losing out on jobs and investment. We continue to press the UK Government to provide a clear and ring-fenced commitment to support the delivery of meaningful renewables capacity.UK ministers have taken powers in the Energy Act 2013 to close the renewables obligation across the UK, meaning that the RO in Scotland will close from 2017. The next three years will be an important transition period, as developers and investors adjust from the tried and tested RO to the entirely new and innovative CFD. The order will partly implement those important transition arrangements. They are largely technical changes, which allow developers to make a one-off choice between the RO and the new CFD scheme in certain circumstances. The changes will also prevent duplication of support for the same electricity by ensuring that generation that is supported under electricity market reform is not eligible for renewables obligation certificates.In conclusion, the changes will improve the efficiency and sustainability of the obligation and will ensure that the legislation remains fit for purpose. In the remaining time available for the RO, we want to continue to attract investment in the right kind of projects and continue the progress that we are making towards meeting our important targets while keeping cost increases for consumers to a minimum.Before I formally move the motion recommending that the order be approved, I am of course happy to respond to any questions that members might have.