Wednesday 11 December 2013 Public Audit Committee About 10:00 Committee business 11 contributions · 6 speakers

Speakers

Choose an MSP to read only their contributions

The record

11 contributions
Hugh Henry Lab The Convener · Renfrewshire South
link

Agenda item 2 is a section 23 report. Members have an update from the Scottish Government on issues that were raised in the Auditor General for Scotland’s report “Commonwealth Games 2014 Progress Report 2: Planning for the delivery of the XXth games”.I have to say that what we are reading is very encouraging. The games are a huge undertaking and all the partners have worked well together, from the Scottish Government down to the implementation team, which is doing a terrific job. I give all credit to Glasgow City Council, which has pulled out all the stops. Anyone who has been in and around the east end of Glasgow recently will have seen that the infrastructure is absolutely fantastic and the facilities are outstanding. Everyone involved is to be commended.I am sure that there will be a slight niggle here or there—you never have a major event without something like that—but on the whole it has been a tremendous achievement.

Mary Scanlon Con Highlands and Islands
link

I agree totally. I associate myself with your comments, convener.We should ask for updates on the security issue. The second-last paragraph of the Scottish Government update, which is annex A of paper 1, says that 13 private security companies have been contracted. Paragraph 3.9 of the Commonwealth Games Federation co-ordination commission’s report, which is paper 2, is on security. A significant amount—was it £90 million?—was allocated to Police Scotland in the early days. Paragraph 3.9 says:“There is going to be a short-fall in security guarding requirements and ... partners are now engaged in high-level discussions on how that can be redressed by a different workforce mix than was previously envisaged.”There were issues regarding security at the Olympic games in London and I know that everything is being done to ensure that we do not face the same problems. However, that seems to be one of the niggles—as you put it, convener—that needs to be addressed. Could we have an update on that?

Hugh Henry Lab The Convener · Renfrewshire South
link

Yes. That would be worth asking for. Security is a sensitive issue, and we remember the arguments and disputes that broke out at the beginning of the Olympics. Thankfully, the games all went smoothly. We need to make sure that security is in place.There is always a background security issue that becomes attached to any major public project. For many years, the police have had concerns about some of the smaller, more local security companies, such as those involved in the guarding of housing association or housing development building sites or, indeed, sites for range of projects. We hope that the police are able to have an influence on how contracts are awarded, but this is a bigger issue than that. We can write to the Scottish Government, to ask for clarification and to be kept up to date on progress.

Tavish Scott LD Shetland Islands
link

I echo the point about security. The budget is £90 million, of which it would be helpful to have a breakdown. I presume that that is available, given that the submission was made and the Government—no doubt sensibly—accepted it.The update to the committee from the Scottish Government, which is not dated, mentions in the section on public transport enhancement plans that the games organisers“are currently waiting for First ScotRail to ... submit their costed train plans to Transport Scotland.”Those were due at the end of November and we are now in December, so I assume that that submission has been made. However, it might be helpful for the committee to be told whether that work is under way.

Hugh Henry Lab The Convener · Renfrewshire South
link

Okay. We can ask about that.

Bob Doris SNP Glasgow
link

Following on from Mary Scanlon’s point on security, I see that, immediately after the part that she quoted, the report from the co-ordination commission says that the issues should be resolved imminently—“before Christmas”. In any letter that we write, it might be worth asking the Government to write back and update us once they are resolved, otherwise we could end up sending two letters. If we send a letter now, it might write back in January saying that the matter will be resolved in two weeks’ time. We could say in our letter that we note that the issues are to be resolved imminently and ask the Government to write back to us as soon as they are resolved. We could also ask for a budget breakdown—Tavish Scott makes a reasonable point about that. We do not want to have to send two pieces of correspondence.

Hugh Henry Lab The Convener · Renfrewshire South
link

I am sure that the clerks will draft something appropriate.

Willie Coffey SNP Kilmarnock and Irvine Valley
link

I see from the papers that we are heading for a fantastic games for Scotland. An issue that caught the attention of the Public Audit Committee in the past was progress at Hampden, on which the Scottish Government’s paper comments that the organisers expect to get decisions on all the planning applications by the end of the year. Will we receive any further updates on progress between now and the Commonwealth games, or is this it until the games, which we look forward to, begin?

Hugh Henry Lab The Convener · Renfrewshire South
link

I suspect that we will not get any more progress reports, as all the attention must now be on delivery. All the major milestones have been reached and the targets have been achieved, although we are still to receive a wee bit of clarification on one or two things. Generally, there is not much more for us to hear. Audit Scotland has confirmed that it will provide a final performance report on the games after the event.

Colin Keir SNP Edinburgh Western
link

That was an issue for me, too. What is being done at Hampden—the improvements to the ground, the installation of the track and all the rest of it—is key to the showpiece events of the games. As far as I am aware, however, the method that is being used has not been used before to produce an international track of that standard, and it would have been interesting if we could have got an idea of just how things are progressing and whether there have been any problems.

Hugh Henry Lab The Convener · Renfrewshire South
link

We must be realistic and consider the role that Audit Scotland would play in that. I think that that is not for Audit Scotland, but for the organising committee, the city council and others, including the Scottish Football Association. We are not a body with responsibility for managing or supervising the delivery of the games, and we have done what we needed to do in terms of the broader financial perspectives and management of resources. Audit Scotland has played its role and the rest will be considered thereafter.We will seek the clarification that has been requested. Other than that, we note the report and wish everyone well for what I am sure will be a hugely successful games that will put Scotland on the map.

  1. 10:00 Decision on Taking Business in Private Procedure · 1
  2. 10:00 Section 23 Reports Committee business · 11
  3. 10:00 Section 23 Reports Committee business · 6
  4. 10:00 Section 23 Reports Committee business · 6

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.