Jim Hume LD South Scotland
link

To ask the Scottish Government whether it will provide an update on progress with the construction of the Borders railway. (S4O-03368)

Keith Brown SNP The Minister for Transport and Veterans · Clackmannanshire and Dunblane
link

The construction of the Borders railway remains on schedule for completion in June 2015, with passenger services available by September 2015 following a period of driver training. We continue to examine with Network Rail possibilities for completion ahead of those timescales.

Jim Hume LD South Scotland
link

I welcome the project’s continuing progress. The minister may be aware that it now takes an hour longer to travel from Hawick to Edinburgh via public transport than it did in 1969. The Borders railway will deliver an undoubted economic boost along its route.

The First Minister said in April that the Borders railway will act as a catalyst for the rest of the historical Waverley route. Will the minister commit to commissioning a feasibility study into the extension of the railway to Hawick, at the very least, to support a town that, of course, was most affected by Beeching’s cuts?

Keith Brown SNP The Minister for Transport and Veterans · Clackmannanshire and Dunblane
link

The member is right to highlight the benefits that will flow from the project, not least because people who have been disconnected from the railway network for nearly 40 years will be able to use the services, which will be frequent and moderately priced.

On further extensions, we have found it productive to concentrate on the project in hand to ensure that we get it done as quickly as possible and in the right and best possible way. The question that the member raised about further extensions was raised last night at the cross-party group on rail and I undertook to look into it and get back to the person concerned. I am happy to copy the member into that correspondence.

Tricia Marwick The Presiding Officer · Mid Fife and Glenrothes
link

I call Mark Griffin, if it is about the Borders railway.

Mark Griffin Lab Central Scotland
link

It certainly is, Presiding Officer.

As far as I understand, the First Minister has already committed to a feasibility study on extending the line in the future. Would that lead to the line being double tracked along its whole length? Would there be significant engineering works to add to the current package if any extension was proposed?

Tricia Marwick The Presiding Officer · Mid Fife and Glenrothes
link

Minister, it was about the Borders railway.

Keith Brown SNP The Minister for Transport and Veterans · Clackmannanshire and Dunblane
link

Indeed it was, Presiding Officer.

Part of the current project will be double tracked but, to go ahead with the project, it was essential to get the necessary cost benefit ratio so that the project washed its face. Had we committed to double tracking the entire line, the cost benefit ratio would have been completely skewed. Further decisions on future double tracking will be taken some time after the project has bedded in.

The same applies to possible extensions. The First Minister has mentioned that extension is a possibility, but we are concentrating on making sure that we get the current project done as quickly as possible.

Motions, questions and votes

Linked from this item of the Official Report
  1. Culture and External Affairs Questions · 1
  2. Ireland (Cultural Links) Questions · 5
  3. Independent Scotland (Common Travel Area) Questions · 4
  4. Dundee (City of Culture 2017 Bid) Questions · 4
  5. Traditional Music (Promotion of Scottish Culture) Questions · 4
  6. Independent Scotland (Cost of International Development Agency) Questions · 6
  7. Independent Scotland (Lottery Funding for Creative Organisations) Questions · 4
  8. Consular Representatives (Engagement on Case for Independence) Questions · 4
  9. Scottish Sport Relief Home and Away Programme Questions · 4
  10. Artworks and National Treasures Questions · 4
  11. Housing (Rising Rents) Questions · 6
  12. Borders Railway Questions · 8
  13. Stranraer Waterfront Development Questions · 4
  14. Affordable Housing (Private Rented Sector) Questions · 4
  15. Transport Scotland (Meetings) Questions · 6
  16. Affordable Housing (Highlands and Islands) Questions · 6
  17. Cycling Infrastructure Questions · 6
  18. “Below the Breadline” Questions · 6
  19. Transport Developments (Aberdeen) Questions · 4
  20. Scotland’s Future Debate · 122
  21. Business Motion Business motions · 1
  22. Parliamentary Bureau Motions Business motions · 2
  23. Decision Time Decision time · 11
  24. Rana Plaza Disaster (First Anniversary) Members’ business · 6
  25. Correction Procedure · 1

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.