8. To ask the Scottish Government when the first phase of the Edinburgh to Glasgow improvement programme will be delivered. (S4O-02269)
Official Report · Chamber
Edinburgh to Glasgow Improvement Programme
Portfolio Question Time
Speakers
Choose an MSP to read only their contributions- Hanzala Malik Lab 2
- Keith Brown SNP 2
The record
4 contributions8. To ask the Scottish Government when the first phase of the Edinburgh to Glasgow improvement programme will be delivered. (S4O-02269)
link
As I told Parliament during the rail debate on 30 May, our electrification programme is making good progress. The electrification of the Whifflet and Cumbernauld lines will be completed in time for the 2014 Commonwealth games. The electrification of the main Edinburgh to Glasgow line will be completed by December 2016, and will be followed by the electrification of the Stirling, Dunblane and Alloa lines by December 2018.
Does the minister agree that, after cutting one third of the budget last July, to describe the continuing Edinburgh to Glasgow improvement programme as being “on track” is a little misleading, particularly given the recent statement that passengers will not benefit from shorter journey times and longer trains until December 2018, which is a full two years after electrification? I press the minister to give assurances that he will make every effort to ensure that the programme catches up so that it can be delivered on time.
link
As I tried to draw out in my earlier answer, in important respects we are actually well ahead of schedule. We are some four years ahead of schedule for the Whifflet programme and we have said that we will complete the Cumbernauld line before the Commonwealth games.
A substantial amount of work has already been done. Members who go through Haymarket station can see the work that has been done there. On the Stirling, Dunblane and Alloa lines, which are in my area, bridges in Alloa have already been lifted in preparation for electrification. We are doing everything that we can to progress the programme as quickly as possible.
On the point about cutting the budget by a third, there is no point in spending money for no particular purpose. The £650 million that we are spending on the Edinburgh to Glasgow improvement programme is a substantial sum of money. Consultants have had a hard look at the issue and we are confident that we are spending the right amount of money. The sum represents a huge investment in the infrastructure between Edinburgh and Glasgow, and the benefits of it will arise well before 2016, whether that is from the Cumbernauld line for the Commonwealth games, the Whifflet line, the improved environmental performance of the railways, or improved stations. Progress will happen throughout the project. Of course, we will try to ensure that it happens as quickly as possible.
A substantial amount of work has already been done. Members who go through Haymarket station can see the work that has been done there. On the Stirling, Dunblane and Alloa lines, which are in my area, bridges in Alloa have already been lifted in preparation for electrification. We are doing everything that we can to progress the programme as quickly as possible.
On the point about cutting the budget by a third, there is no point in spending money for no particular purpose. The £650 million that we are spending on the Edinburgh to Glasgow improvement programme is a substantial sum of money. Consultants have had a hard look at the issue and we are confident that we are spending the right amount of money. The sum represents a huge investment in the infrastructure between Edinburgh and Glasgow, and the benefits of it will arise well before 2016, whether that is from the Cumbernauld line for the Commonwealth games, the Whifflet line, the improved environmental performance of the railways, or improved stations. Progress will happen throughout the project. Of course, we will try to ensure that it happens as quickly as possible.
Motions, questions and votes
Linked from this item of the Official ReportIn this meeting
Everything on 19 Jun 2013 →- Rail Infrastructure Investment (Perth to Edinburgh Route) Questions · 4
- Community Transport (Structure and Operation) Questions · 8
- Private Housing Sector (Support) Questions · 4
- Public Transport (Integrated Ticketing and Multimodal Use) Questions · 6
- Living Wage (Public Sector Procurement) Questions · 4
- Cities Strategy Questions · 5
- Edinburgh to Glasgow Improvement Programme Questions · 4
- Superfast Broadband (Shetland) Questions · 4
- International Development Fund (Occupied Palestinian Territories) Questions · 6
- Creative Scotland (Vision Statement) Questions · 7
- BBC Scotland (Budget Reductions) Questions · 6
- Free-to-air Broadcasting (Major Events) Questions · 4
- Arts Festivals (Regeneration Areas) Questions · 6
- European Commission (Meetings) Questions · 6
- Nordic Council (Meetings) Questions · 4
- First World War Commemoration (Conscientious Objectors and Peace Groups) Questions · 4
- Budget Outturn 2012-13 Statement · 23
- Victims and Witnesses (Scotland) Bill: Stage 1 Bill debate · 77
- Minor Standing Order Rule Changes Debate · 4
- Business Motion Business motions · 1
- Parliamentary Bureau Motions Business motions · 2
- Decision Time Decision time · 5
- Credit Union Expansion Project Members’ business · 19
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.