“NHS financial performance 2011-12” (Correspondence)

Wednesday 27 March 2013 Public Audit Committee About 10:00 Committee business 9 contributions · 4 speakers

Speakers

Choose an MSP to read only their contributions

The record

9 contributions
Iain Gray Lab The Convener · East Lothian
link

Agenda item 4 is correspondence from the Scottish Government on the section 23 report “NHS financial performance 2011-12”, following a question raised by Mary Scanlon about capital maintenance backlogs.Does anyone want to raise anything on the correspondence?

Mary Scanlon Con Highlands and Islands
link

The main issue that I asked about was whether the backlog maintenance that we highlighted came from the capital or the revenue budget. The cabinet secretary said in a debate that it came from the capital budget, but I am pleased to see clarification in the third paragraph of the correspondence, which states:“Backlog maintenance is addressed through both the capital and revenue allocations made to NHS Boards.”That was the main issue on which I wanted clarity, and the correspondence makes it much clearer.

Bob Doris SNP Glasgow
link

The response also says that some of the backlog maintenance will be dealt with through the non-profit distributing hub project. In my constituency, in a region in my local area, that means two new-build health centres—Woodside health centre and Maryhill health centre—costing many millions of pounds. I am sure that my constituents will be grateful for that new service.11:15

Willie Coffey SNP Kilmarnock and Irvine Valley
link

I recall the committee’s discussion about the £1 billion backlog issue. The correspondence with Derek Feeley, which is in paper PA/S4/13/5/5, includes a table that shows that the backlog in the high-risk category is £161 million—that is on the fifth page of our paper. I do not dismiss the importance of the other categorisations, but the extent of the problem is not a £1 billion backlog, as reported widely in the media; it is £161 million, which is about a tenth of that. I also recall that, at the time, it was not clear what assets were earmarked for disposal. That is clearer now, as the correspondence covers that issue, too.My attention was briefly drawn to the figures for the various health boards in annex 2 of the letter from Derek Feeley. Some of those figures do not add up. In particular, the NHS Ayrshire and Arran line is incorrect—the sub-total should be £63.3 million, not £93.3 million. That makes the problem a wee bit better, in a sense, because the actual figure is £30 million less than is indicated in the report. I do not know why the figure is wrong, but it is to our benefit.

Iain Gray Lab The Convener · East Lothian
link

Thank you, Mr Coffey. You have not only read the papers, but added up the sums.

Willie Coffey SNP Kilmarnock and Irvine Valley
link

The sums do not add up particularly well. That cannot be explained by the table showing the assets that are held for sale, which is in annex 3. However, although the figures are incorrect, that is to our advantage, in that it lessens the extent of the problem.

Mary Scanlon Con Highlands and Islands
link

The figure of £1 billion is actually in annex 2. I think that it came down to about £0.75 billion, because some of the backlog maintenance related to assets that were fit for disposal. I think that Colin Beattie raised that point.When we talked about the figure of £250 million, that was in the high-risk category. The high-risk figure is £252 million, the figure for significant risk is £289 million, for medium risk it is £272 million and for low risk it is £194 million. The total is more than £1 billion. Therefore, when we talked about high risk, we were not talking about the full extent of the risk. For my part, I was talking about the high-risk category, because that related to the urgent repairs that could affect clinical care and patient health.

Iain Gray Lab The Convener · East Lothian
link

Do members agree to note the correspondence?Members indicated agreement.

Iain Gray Lab The Convener · East Lothian
link

We will now continue in private, so I ask any members of the press or public to leave the room.11:18 Meeting continued in private until 12:46.

  1. 10:00 Decision on Taking Business in Private Procedure · 3
  2. 10:00 Section 23 Reports Committee business · 77
  3. 10:00 Section 23 Reports Committee business · 10
  4. 10:00 Section 23 Reports Committee business · 9

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.