Forth Replacement Crossing

Wednesday 14 March 2012 Infrastructure and Capital Investment Committee About 11:35 Evidence session 86 contributions · 9 speakers

Speakers

Showing Margaret McCulloch only · show everyone

Margaret McCulloch’s contributions

11 contributions
Margaret McCulloch Lab Central Scotland
link

When Transport Scotland officials last appeared before the committee on 7 September 2011 they gave an oral update on the progress of the Forth crossing project. Will you update us on the three main contracts?

Margaret McCulloch Lab Central Scotland
link

Can you highlight any key events that are likely to occur over the next six months of the project?

Margaret McCulloch Lab Central Scotland
link

Before I ask my question on the three contracts, I want to confirm that you are in a position to answer it. Do you manage the other two contracts for the intelligent transport system and John Sisk?

Margaret McCulloch Lab Central Scotland
link

Our briefing notes tell us that a payment of £790 million to the principal contractor was a fixed cost, but they do not say whether the £12.9 million contract for the intelligent transport system and the £25.6 million contract with John Sisk are fixed costs. Are they fixed costs?

Margaret McCulloch Lab Central Scotland
link

Right. Sorry—which one did you say has inflation built into it?

Margaret McCulloch Lab Central Scotland
link

So, the overall total of £828.5 million could rise through inflation.

Margaret McCulloch Lab Central Scotland
link

So, there will be no more to pay above the £828.5 million other than the 8 per cent inflation cost. Do you foresee inflation being higher than 8 per cent?

Margaret McCulloch Lab Central Scotland
link

On subcontractors, you said that you do not go through the procurement process to allocate work to other organisations that have been used before. Is that correct?

Margaret McCulloch Lab Central Scotland
link

Do you go through the procurement process for your subcontractors?

Margaret McCulloch Lab Central Scotland
link

Throughout the procurement process, when you have been allocating work to subcontractors, has any consideration been given to building in initiatives to help sustain the employment of the individuals who are working on the project? It is brilliant that Scotland is benefiting by about £20 million but, in the procurement process, is there an allowance so that people will not find themselves out of work when the project comes to an end? Are there initiatives or projects built in that will sustain those individuals within the community or in other work?

Margaret McCulloch Lab Central Scotland
link

Is it not sad that the Scottish Government did not have the courage to put the welfare of Scotland first and allocate the whole contract to a Scottish company? You say that you employ only 400 people just now. How many people would have been employed if we had managed to allocate the whole contract in Scotland? How many unemployed people would have benefited?

  1. 10:00 Rail Franchise 2014 Evidence session · 126
  2. 11:35 Forth Replacement Crossing Evidence session · 86
  3. 11:35 Subordinate Legislation Subordinate legislation · 1
  4. 11:35 Subordinate Legislation Subordinate legislation · 2

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.