Forth Replacement Crossing (Procurement)

Scottish Executive Question Time General Questions

Thursday 24 February 2011 Meeting of the Parliament Questions 6 contributions · 3 speakers Watch on Scottish Parliament TV

Speakers

Showing Keith Brown only · show everyone

Keith Brown’s contributions

3 contributions
Keith Brown SNP The Minister for Transport and Infrastructure · Ochil
link
The procurement of the Forth replacement crossing project has been separated into three contracts. Tenders were received for the principal contract, which includes the bridge and the approach roads, on 28 January 2011, and they are being assessed. The principal contract is on programme for award in April 2011. The intention is to issue the invitation to submit final tenders for the Fife intelligent transport system contract this week, and for the M9 junction 1A contract in early April. Those contracts are on programme for awards in May and July 2011 respectively.

Keith Brown SNP The Minister for Transport and Infrastructure · Ochil
link
I will deal with the last point first. There were good reasons why that was heard in private, and I do not intend to go further into that issue today. However, I am happy to answer the point about the announcement being made in April. I understand why some people—some in the Labour Party, for example—who see the project as a waste of money should think that there is no real urgency, but most of the rest of us believe that the project is vital. The reason why we have had the dual process of going through Parliament and advancing the procurement process as quickly as we have done is that the project is vital, and the first possible chance that we will have to make an announcement—I think that this has been cleared with the Presiding Officer—is April, shortly after the contracts have been awarded. That is why that is happening. Things are happening as quickly as they possibly can because we see the project as vital.

I am happy to give Margaret Smith the assurance that I gave at stage 3. We are engaging and we will engage. We have already held an event with small businesses to ensure that they can maximise the opportunities that exist for them.

Keith Brown SNP The Minister for Transport and Infrastructure · Ochil
link
We do not want to do anything at this stage that would delay the award of the principal contract in particular. There are also tight timescales for the other contracts, but I am happy to take away Mary Mulligan’s suggestion, ask officials to look into the matter, and come back to her on the substantive issue.

  1. Business Motion Business motions · 4
  2. Regeneration Debate · 120
  3. Third Sector Support 2011-12 Questions · 6
  4. North Lanarkshire Council (Meetings) Questions · 4
  5. Forth Replacement Crossing (Procurement) Questions · 6
  6. Strathclyde Partnership for Transport (Meetings) Questions · 8
  7. Scottish Borders (Economic Development) Questions · 6
  8. St Margaret of Scotland Hospice Questions · 6
  9. Disabled People’s Organisations (Meetings) Questions · 4
  10. Rail Ticket Pricing (Sutherland) Questions · 5
  11. Engagements First Minister’s Questions · 11
  12. Prime Minister (Meetings) First Minister’s Questions · 6
  13. Secretary of State for Scotland (Meetings) First Minister’s Questions · 14
  14. Universities (Support) First Minister’s Questions · 8
  15. INEOS and PetroChina (Meetings) First Minister’s Questions · 4
  16. Wind Turbines (Forestry Commission) First Minister’s Questions · 7
  17. Point of Order Procedure · 4
  18. Domestic Abuse Questions · 10
  19. Crime Levels (North Ayrshire) Questions · 6
  20. Community Safety (Prisoner Release) Questions · 4
  21. Community Court (Glasgow East End) Questions · 4
  22. Scottish Police Services Authority (Staff Regrading) Questions · 4
  23. Voluntary Groups Funding (Crime Reduction and Prevention) Questions · 6
  24. Large-scale Biomass Plants (Timber Industry) Questions · 6
  25. Wildlife Corridors Questions · 8
  26. Dairy Farmers, Retailers and Processors (Meetings) Questions · 6
  27. Food and Drink Sector Questions · 4
  28. Common Agricultural Policy Questions · 4
  29. Common Agricultural Policy Questions · 4
  30. Flooding (Moray) Questions · 4
  31. Patient Rights (Scotland) Bill: Stage 3 Bill debate · 39
  32. Patient Rights (Scotland) Bill Bill debate · 20
  33. Business Motion Business motions · 1
  34. Parliamentary Bureau Motions Business motions · 2
  35. Decision Time Decision time · 9
  36. Coalfields Regeneration Trust Members’ business · 16

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.