Forth Crossing Bill

Wednesday 15 December 2010 Meeting of the Parliament Bill debate 27 contributions · 13 speakers

Speakers

Showing Keith Brown only · show everyone

Keith Brown’s contributions

4 contributions
Keith Brown SNP The Minister for Transport and Infrastructure · Ochil
link
It is important to reflect, at stage 3, on why we introduced the Forth Crossing Bill. The problems with the Forth road bridge are well known. Should the crossing be restricted or not available, there will be dire economic and social consequences. That cannot be allowed to happen. Our manifesto therefore committed us to a replacement Forth crossing, and we took action.

In 2007, we developed our proposal. In 2008, we confirmed retention of the Forth road bridge as part of a public transport corridor. In 2009, we introduced the Forth Crossing Bill, which, this year, has been subject to detailed public and parliamentary scrutiny. The bill withstood that examination. In 2011, we will build. In only four years we have gone from initiation to construction. The Government recognises the issues. We have acted quickly, and we have delivered.

Like other members, I never forget that we are making legislation for and on behalf of the people of Scotland. Accordingly, we must engage with those who will be directly affected by it, and we have done so. We have listened, and we have reflected. As the committee graciously acknowledged in its report, we have made a host of significant, positive changes. They include changes to improve design, changes to improve mitigation and changes to improve monitoring, reporting and community engagement.

The hybrid bill procedures, which were applied here for the first time, present undoubted challenges, particularly for objectors. Substantial periods of time have been given to investigating complex matters, some of which are deeply sensitive for individuals. I am sure that we can all learn lessons from the process. However, the process has been thorough and exacting.

It is important to acknowledge the contribution of those who have shaped the bill and its associated code of construction practice. Although I will mention him again in my summing-up speech, I mention first the efforts and diligence of Stewart Stevenson in getting us to this stage. I also thank publicly the many individuals, community councils, local authorities, businesses and associations that have actively engaged in the process. We might not always have agreed, but their contributions and advice were much appreciated, and our proposals are better for that engagement.

It would be remiss of me if I did not mention the people within the Parliament who have done a lot of hard work to improve the bill, including the Finance Committee, the Subordinate Legislation Committee and the Transport, Infrastructure and Climate Change Committee, for their considered analysis. I also acknowledge the leading roles of Mary Mulligan and Margaret Smith in representing their constituents in Newton and South Queensferry. I am sure that the Parliament will join me in paying tribute to the skill and rigour of the Forth Crossing Bill Committee, expertly led by Jackson Carlaw, in scrutinising the bill.

This is a good bill. Together with the associated code of construction practice, the bill is the better for the exacting scrutiny to which it has been subject. The code sets out precisely how the contractor should undertake the works, and it enables full scrutiny and transparency of actions. In so doing, it rightly provides the highest possible levels of protection for the public.

The construction task itself will be huge. It will be, as has been said many times in the media, the biggest single project in Scotland for a generation. The bridge construction will take between five and six years, and our code of construction practice addresses mitigation measures to minimise disturbance over that period. We are also investing in public transport measures. We will implement bus hard shoulder running on stretches of the M90 and M9, and we are working with Fife Council to deliver Halbeath park and ride. Those and other measures will assist traffic flows during the construction phase and beyond.

We will set very high standards in the provision of information. I can confirm that we will establish a contact and education centre at the current offices of the Forth Estuary Transport Authority at South Queensferry, which will be a focus for interested individuals. We are providing accessible engagement and information, because information and providing public protection will be at the heart of this vital project.

The bill is absolutely necessary. The Forth replacement crossing project is absolutely vital for ensuring Scotland’s economic wellbeing. Accordingly, I commend the bill to the Parliament.

I move,

That the Parliament agrees that the Forth Crossing Bill be passed.

16:13

Keith Brown SNP The Minister for Transport and Infrastructure · Ochil
link
The member should be heartened by the experience with the Clackmannanshire bridge, which was delivered on time and on budget.

As I may have other points to address when I sum up, I confirm that the new VAT rate will be applied to the project, but we have reviewed the matter and are confident that expenditure can be kept within the present envelope.

Keith Brown SNP The Minister for Transport and Infrastructure · Ochil
link
I have enjoyed listening to the debate. If the truth were told, I have enjoyed listening more than speaking, because my voice is not doing well. I am glad that I have a couple of quiet days ahead of me on Thursday and Friday.

Before responding to individual comments, I will make some important points. It would have been better if more members had been in the chamber. As many members have, I record my thanks and admiration for the work that my good friend and colleague Stewart Stevenson undertook. If the bill is passed today, it will be due to a recognition of, and a worthy testament to, his drive, enthusiasm and dedication to the project. His involvement and leadership in delivering the project from development to design and through the bill process were considerable. I am sure that all members acknowledge his substantial contribution.

There is general consensus on the bill albeit, sadly, with one or two notable exceptions. I thank Parliament greatly for its interest and support. This is a proud day for Stewart Stevenson—it should be—for the Parliament and, most important, for Scotland. This is the day when Scotland commits to a world-class structure across the Forth. As a couple of members have mentioned, we will have three bridges—three iconic designs made over three centuries—in one splendid Scottish setting. This is not only about structures. Beautiful though they are, such structures are merely a means to an end in which our purpose is, of course, to secure our future economic and social wellbeing, thereby providing an inclusive and economically vibrant Scotland.

A number of points were raised in the debate and I will try to address them. In his summing up, Charlie Gordon referred to the Cabinet Secretary for Finance and Sustainable Growth as being “enervated”. I have never seen John Swinney enervated. I have seen him energised perhaps, but I have to say that: he is my boss. Charlie Gordon made a number of interesting points, to which I will come back. He also touched on points that members who spoke before him had made, not least of which were Jim Tolson’s points on the Halbeath junction and Rosyth. The Halbeath commitment remains in place and there will be further discussion on the matter with Fife Council. We cannot put a price on the works until we have had that discussion. I cannot say just now whether we can commit to Rosyth. We do not yet have sufficient details from the council on that, but I am content to explore the option, while being mindful at all times of funding constraints. We will explore the option as best we can as things go on.

I say to Mary Mulligan that we are providing a link from the new bridge to the M9, using the existing asset of the M9 link. I remind her that we are making improvements to traffic management in Newton: we will sign traffic from the M9 through to Newton. I mentioned earlier the funding commitment that we will make.

I say to Dave Stewart that we are confident that we will be able to sign the contract in April; we are very confident on that and we want to do it because we can then commence work in the summertime. David Stewart also asked about EU funding applications. We have done that but, unfortunately, we were unsuccessful. He also made a point on regular updates to committees. I will continue the commitment that Stewart Stevenson gave previously; Dave Stewart will be aware of the updates that Stewart Stevenson has already given. We will provide six-monthly updates.

Dave Stewart also spoke of his concern about the two consortia that are bidding for the project. My view is that there is very little likelihood that either would like to withdraw, given how much they have already put into the process that—of course—started quite some time ago. He also made a reasonable point on the adopt an apprentice programme. That issue is one for my colleague Angela Constance, who has the skills remit. We continued the programme this year, but whether it will continue in the future depends on budget constraints. I will ensure that my colleague takes up the point.

A number of members made the point to Patrick Harvie that the real risk is that, if we were to wait until we had checked the cabling—which will happen in 2012—and the results were wrong, we would not have enough time to build the new bridge. If we do that, we will stand to be condemned by everybody in Scotland.

Keith Brown SNP The Minister for Transport and Infrastructure · Ochil
link
The member should know that the cable inspection results will not be known until 2012. This is not only about cabling. As, I think, Margaret Smith said, it is about other aspects of the bridge, too. We cannot risk not having a replacement crossing in place by the time drastic action needs to be taken in terms of remedial work to the cables and elsewhere on the existing bridge.

In approving the bill to construct the bridge, Parliament will be protecting and investing in the economic wellbeing of Scotland. We will be protecting and investing in our future—Scotland’s future. In voting for the bill today, we reaffirm our commitment to our collective future. As I said, we are building an iconic bridge—the third such bridge across the Forth.

Before I finish, I should say that I appreciate Ted Brocklebank’s statement on iniquitous tolls. I very much agree with him: we should not have iniquitous tolls on any bridge in Scotland. I worked very hard on that in the past.

As I said, in voting for the bill today, we reaffirm our commitment to our collective future. All that remains is for me to ask Parliament to formally support the motion.

  1. Time for Reflection Time for reflection · 3
  2. Business Motions Business motions · 4
  3. Junior Scottish Minister Debate · 9
  4. Damages (Scotland) Bill:Stage 1 Bill debate · 27
  5. Forth Crossing Bill: Stage 3 Bill debate · 32
  6. Forth Crossing Bill Bill debate · 27
  7. Business Motion Business motions · 1
  8. Decision Time Decision time · 4
  9. RAF Leuchars Members’ business · 10

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.