To ask the Scottish
Executive whether it plans to rule out delaying the completion of the M74 junction 5 Raith scheme until 2013-14. (S3O-10380)
Official Report · Chamber
Scottish Executive Question Time General Questions
To ask the Scottish
Executive whether it plans to rule out delaying the completion of the M74 junction 5 Raith scheme until 2013-14. (S3O-10380)
We are considering the benefits of combining the M74 Raith junction scheme with the M8 Baillieston to Newhouse scheme and the M8, M73 and M74 network improvement schemes as a single contract to be funded by a non-profit-distributing model. The M74 Raith programme would be tied to the M8, a decision on which will be made shortly.
If the Raith interchange scheme is put back on to the same timescale as the M8 Baillieston to Newhouse scheme, thus delaying it a year, what additional costs will fall on the Raith scheme? Can the minister guarantee that both schemes or the combined scheme will be ready in time for the 2014 Commonwealth games in Glasgow?
By consolidating many items of work into a single non-profit-distributing model, we are able to achieve economies of scale and reduce and manage the costs in an appropriate way. We have reached the point where we have all but completed the planning issues that are associated with that. We expect to make the remaining orders. We are making the best possible speed in bringing forward a long-awaited project.
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.