Earlier this week, the Glasgow 2014 organising committee announced an increase in the overall budget for the games. The additional budget was required mainly in response to an increase in broadcasting costs and the need to set aside a greater contingency fund. The new games budget is still only one 20th of the public funding that is being provided for the 2012 Olympics. The Scottish Government's contribution has risen by £59 million to £297 million at 2007 prices. That necessary increase is challenging for the public purse, but the funding boost will help us to stage an event that will have lasting benefits for generations to come. The games are good news for Glasgow and Scotland, which is why we have also recently launched a £23.5 million legacy plan for Scotland to capitalise on the opportunities of 2014.
I want to ensure that, in terms of its budget, Glasgow's Commonwealth games is treated equally with the London Olympics by the United Kingdom Government. Will the First Minister back my call for Glasgow City Council to join me and the Scottish Government in insisting that the £300 million that is owed to Scotland through London Olympics regeneration funding is paid to Scotland? Will he also ensure that a significant share of those funds—if they are recovered—will be used for regeneration projects in Glasgow to build a lasting legacy of the 2014 games? I fear that, if that does not happen, the UK Government will not only rip off Glasgow, but will let down Scotland.
Glasgow City Council and the Scottish Government are co-operating fully on delivering the Commonwealth games for Scotland, as we demonstrated at a press conference in Glasgow on Monday. Nonetheless, I thank Bob Doris for his question and the points to which he has drawn attention.
I find it disappointing that Jim Murphy and Gerry Sutcliffe cancelled the meeting with the Minister for Public Health and Sport on 10 November to discuss the return of £150 million of lottery money to Scotland. Scotland is losing out not just on the lottery money, but on another £165 million because of the UK Government's decision not to subject regeneration expenditure on the Olympics to the Barnett formula in the normal way. There should be support across the chamber, not just from Glasgow City Council, for Scotland to get its fair share. It is about time the United Kingdom Government stepped up to the plate on the issue and stopped ripping off Scotland.
Alex FergussonThe Presiding Officer · Galloway and Upper Nithsdale
Several members want to ask supplementary questions on this important matter, and I am keen to allow as many as possible. Questions should therefore be short and sharp, as should the answers.
Although we all want to see Glasgow hosting the best ever Commonwealth games in 2014, what specific guarantee can the First Minister give to council tax payers in Glasgow and all other taxpayers throughout Scotland that the increase of £81 million will be the final such increase?
What was announced on Monday was the result of many months of careful work. I have every confidence—as has Glasgow City Council—in the audit that has been done of the expenditure that needs to be devoted to the games.
Some people have argued that the broadcasting costs should have been better anticipated—I saw that argument deployed in one of our newspapers. The Government inherited the estimate that broadcasting rights would offset broadcasting costs on the home broadcaster, and I have no complaint whatever with the estimate that was formulated in 2007, which was based on the experiences of Manchester in 2002 and of Melbourne in 2006. It was an entirely reasonable estimate to make at the time—indeed, I still hope that the BBC can be prevailed upon to give Scotland the same treatment for 2014 as Manchester received for 2002.
The Government reports of the overspend stated that £20 million of the £81 million that was needed to fill the gap would come from a reserve fund. Should further contingencies arise, how much will be left in the reserve fund?
There are two aspects: there is a contingency fund of £80 million, which has received a £48 million increase as a result of the announcements on Monday, and there is a reserve fund of £20 million beyond that. The reserve fund is the only part of the funding that does not ascribe to the formula of 80 per cent coming from the Scottish Government and 20 per cent coming from Glasgow City Council. The reserve fund is funded entirely by the Scottish Government and the Scottish public purse. I think that that is right and proper, because although the benefit of the games will be felt predominantly in the city of Glasgow, their underlying benefits will stretch across the country.
At a time of severe pressure on the public purse, meeting the obligations will undoubtedly be a huge strain. Nonetheless, we should keep our eyes on the prize—the prize for Scotland is enormous. This major international event is going to have enormous beneficial effects not only on infrastructure and immediate building but for future generations of young Scots.
Does the First Minister appreciate the deep frustration that is felt by those of us in Glasgow who have worked so hard to bring the Commonwealth games to the city at his attempts always to pass the buck and blame other people whenever we raise an issue about them? Whether he likes it or not—
Alex FergussonThe Presiding Officer · Galloway and Upper Nithsdale
How does the First Minister square in his own mind this great commitment that he parades so publicly with the cancellation of the Glasgow airport rail link project which, as he knows, was a vital part of the bid document? Will he attempt to reinstate his credibility by reinstating the GARL project?
Margaret Curran's view is not shared by the Commonwealth Games Federation, which pointed out that the project was not an integral part of either the games bid or their successful delivery. Now that the smoke of by-election has cleared, I hope that even the constituency member will somehow concede that the billions of pounds of infrastructure investment that is now being made in and around Glasgow is ample demonstration of this Government's commitment to that great city. Prime among these projects is, of course, the M74 motorway, which has been awaiting completion for the best part of 40 years and which will, under a Scottish National Party Government, finally be finished.
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.