Dalkeith Bypass

SCOTTISH EXECUTIVE Enterprise, Lifelong Learning and Transport

Thursday 9 February 2006 Meeting of the Parliament Questions 8 contributions · 4 speakers

Speakers

Choose an MSP to read only their contributions

The record

8 contributions
Rosie Kane SSP Glasgow
link
To ask the Scottish Executive whether, in light of the report on the environmental impact of the Dalkeith northern bypass by WA Fairhurst & Partners, it will cease work on the project. (S2O-8993)

Tavish Scott LD The Minister for Transport and Telecommunications · Shetland
link
No.

Rosie Kane SSP Glasgow
link
Well, is that not pathetic? The minister has given a one-syllable answer to a question on contaminated land. We are talking about contaminants that could be carcinogenic and the minister gives a one-syllable answer. Shame on him. I will continue with more than one syllable, as usual.

In light of the fact that the Fairhurst report stated that additional potentially contaminated sites have been identified along the route since the 1995 assessment, and in light of the contamination along the proposed route of the M74 northern extension, will the minister explain why the Executive refuses to abide by the precautionary principle, continues to ignore the mounting evidence of contamination in Scotland and continues to build roads that merely contribute to increased pollution for our communities—rather than serve them, which is what the minister was elected to do?

Tavish Scott LD The Minister for Transport and Telecommunications · Shetland
link
I thought that we would get some rewards for giving straight answers, but obviously not from the Scottish Socialist Party. I am afraid that Ms Kane wilfully misrepresents the report that she alleges to know something about. The environmental mitigation report prepared by WA Fairhurst & Partners does not support the ground investigation carried out on the scheme and, in that sense, it is clear that the findings are not as Ms Kane has indicated. The Scottish Environment Protection Agency, East Lothian Council and Midlothian Council were consulted as part of the new environmental mitigation report and assessment. No land in the corridor occupied by the A68 Dalkeith northern bypass has been designated as contaminated land under the terms of the Environmental Protection Act 1990. We have to deal in facts, even if Ms Kane does not.

John Home Robertson Lab East Lothian
link
There have already been several environmental impact inquiries into that development. Will the minister take it from me and from Rhona Brankin, the local constituency member, that there is overwhelming public support in and around Dalkeith for a bypass that will relieve serious congestion and pollution? What has been the cost of dealing with protesters who know little and care less about pollution in the Dalkeith area? Can residents and commuters in Midlothian and East Lothian have an assurance that the bypass and long-overdue improvements to the Sheriffhall junction will be constructed without further delay?

Tavish Scott LD The Minister for Transport and Telecommunications · Shetland
link
The cost about which John Home Robertson inquires is in the region of £1.9 million, although we have yet to receive final figures, due to the assessment process that has to be followed. The benefits of the scheme are widely understood and acknowledged, and he makes an extremely important point about the benefits to people who live in Dalkeith. It would seem that some people would very much like to see heavy goods vehicles continue to trundle through Dalkeith, but I think that most of us agree that that would not be good for local people. That is why, for some years now, there has been a strategic roads need to make the investment that we are now making.

Mark Ballard Green Lothians
link
Does the minister recognise that the report clearly states that the bypass will lead to the loss of valued woodland and that the authors admit that there is need for further investigation into potential contaminated land, which could contain mercury, arsenic and phenol? Does he further recognise that many of the people who felt that they had no option but to demonstrate on the site were local people who were worried about the impact of the bypass on their lives, and that without the multimodal study that was promised by Sarah Boyack in 1999 it is impossible to tell whether that bypass is the most effective way to relieve the genuine problems created by trucks and the like going through the centre of Dalkeith? Without that multimodal study, surely any attempt at a bypass would be reckless and ill judged.

Tavish Scott LD The Minister for Transport and Telecommunications · Shetland
link
It would be reckless and ill judged to ignore the Scottish Environment Protection Agency, which Mr Ballard clearly wishes to do, and to ignore East Lothian Council and Midlothian Council. All those bodies were consulted as part of the environmental mitigation report that I mentioned, which found that there is no need to designate land as contaminated land under the terms of the Environmental Protection Act 1990. I believe that that is the factual position, and I think that it is important to base any view on the issue on the facts that are presented under that act. I can only commend that approach to Mr Ballard. I cannot agree with his other assertions, other than to say that of course people have a right to make clear their views on any road proposal. However, it is important to recognise the benefits that the measure will bring to the centre of Dalkeith, and Mr Ballard continues to minimise those benefits.

Finally, it is not true to say what Mr Ballard has said—not for the first time—about the Dalkeith estate park. The scheme does go through the estate, but it does not affect the Dalkeith country park, because it passes to the north of that. Again, that is an important fact that should be borne in mind.

  1. Scottish Parliament Thursday 9 February 2006 Debate · 1
  2. Business Motion Business motions · 4
  3. Budget (Scotland) (No 3) Bill: Stage 3 Bill debate · 10
  4. Budget (Scotland) (No 3) Bill Bill debate · 57
  5. Volunteering Debate · 49
  6. School Curriculum (History) Questions · 9
  7. Play Opportunities Questions · 6
  8. Social Housing (Edinburgh) Questions · 5
  9. Fuel Poverty Questions · 6
  10. Schools (Devolved Management and Budgets) Questions · 8
  11. Ayr Hospital Questions · 6
  12. Cabinet (Meetings) First Minister’s Questions · 10
  13. Prime Minister (Meetings) First Minister’s Questions · 13
  14. Secretary of State for Scotland (Meetings) First Minister’s Questions · 6
  15. Utility Charges First Minister’s Questions · 6
  16. Life Expectancy First Minister’s Questions · 4
  17. National Grid (Renewable Energy) First Minister’s Questions · 8
  18. SCOTTISH EXECUTIVE Questions · 1
  19. Well-paid Jobs Questions · 6
  20. Edinburgh to Bathgate Rail Line Questions · 8
  21. First Bus (Meetings) Questions · 6
  22. Buses (Accessibility) Questions · 6
  23. Dalkeith Bypass Questions · 8
  24. Road Safety (Dumfries and Galloway) Questions · 6
  25. Extraordinary Rendition Questions · 8
  26. Noise Nuisance Questions · 6
  27. Vulnerable Witnesses (Scotland) Act 2004 Questions · 4
  28. Rural Policing (Strathclyde) Questions · 4
  29. Jury Selection Questions · 6
  30. Scottish Police Federation (Meetings) Questions · 8
  31. Social Work Debate · 54
  32. Decision Time Decision time · 7
  33. Cumbernauld Town Centre Members’ business · 30

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.