Accountability, surely?
Official Report · Committee
Holyrood Project
Speakers
Choose an MSP to read only their contributions- Mr Russell 83
- Nick Johnston Con 45
- Dr Gibbons 27
- Andrew Wilson SNP 22
- Brian Adam SNP 19
- Margo MacDonald SNP 19
- Mr Black 16
- Paul Martin Lab 11
- Euan Robson LD 10
- Cathie Craigie Lab 10
- Margaret Jamieson Lab 9
- Karen Whitefield Lab 7
- Mr Gordon 5
- Mr Robert Black Auditor General for Scotland 1
- Mr Muir Russell Permanent Secretary, Scottish Executive 1
- Dr John Gibbons Chief Architect, Scottish Executive 1
- Mr Robert Gordon Head of Executive Secretariat, Scottish Executive 1
The record
292 contributions · showing 201–292I was not spending that money and I was not signing cheques. The project was still at a pretty early stage, well in advance of tender documents or designs that would have led to spend. The notion that there was accountability for money that was going out the door is not valid.We are in hindsight world here. If I had known all this, I would probably have breathed very heavily on the project team and said, "Keep on keeping on; I want to see you getting the costs back down."
I must insist that we move on to ask about insufficient accounting for risk.
The report said that the procurement strategy lacked a systematic assessment of the risks to the project. What was your appreciation of the risks in the chosen procurement route—designer appointment and subsequent construction management—and how did you plan to manage the risks, given that no systematic assessment was made?
We have already discussed the construction management route and have established that it provided flexibility to cope with the evolving nature of the project. I hope that we have established that nobody thinks that that was wrong. The fundamental question of assessing risk at the beginning is logical and acceptable for particular projects and contracts. However, at the very earliest stage, when discussing working to a target budget, I find it difficult to accept the practice of adding on another number. I suggest that it makes it harder for the project team to live with the basic target if one lets it be known that one has another £N million in one's back pocket. As I said, the team was trying to manage the project down to meet the target figure. However, people recognised that the project would have many uncertainties and that many questions would be asked about the standard of construction and the implications of having a high-quality architect and of opting for a high-quality project. The figure of £50 million recognised those features of the project and took into account the costings that we knew about from high-quality projects that we had seen, such as the prestige court projects with which John Gibbons and his colleagues were familiar. It was not as though the project were proceeding on the basis that there was no risk and that it would be clean, tight and low cost. People were building with the notion that this would be a quality project and had to be priced accordingly. To that extent, there was a realistic basis for the £50 million figure.As the project proceeded, towards spring 1999 people began to say that the handover figure would include extra things, such as the increase in area. At that point, it was perfectly reasonable, with stage D imminent and the design that much clearer, to begin to think in terms of a more specific contingency. In the figures that built up from the £62 million that led to the £109 million, which was the handover figure, members will find a £6 million contingency figure. That is the standard 10 per cent; from memory, I can say that the current figure for the augmented and changed project is also 10 per cent. As I said when I was talking about the emergence of the stage D design and costs, people were getting ready to put in the disciplines of managing the more specific design and contracts that were to arise. That is where risk assessment and value engineering come in.At the current stage, as tenders are put out and come back, techniques such as risk assessment are at the heart of how the professionals react to what is happening and how they judge what the project will cost. That will be relevant to the questions that the committee may want to ask about the current state of the project and its progress.The situation has evolved from targeting, based on something reasonably sound, through an acceptance of changes to a more conventional approach, including a contingency element. That is the process that has taken place and that no doubt continued after the quantum shift from June 1999 to the June 2000 sign-off of the new stage D, which is so dramatically different.
I would have thought that the early stages to which you are saying it is not legitimate or realistic to apply a risk assessment are the very stages where such an assessment is necessary. Surely, when dealing with such an open-ended project, a contingency well beyond that of 10 per cent, which is in place now the plans are firmer, should apply at an early stage.Why was the Treasury guidance not considered? Did you raise with the Treasury the fact that you did not think that the guidance was reasonable? Do you pick and choose what guidance to follow depending on the project? The whole point of having the guidance is that there can be—and have been—significant overruns in such public sector projects. The point of a risk assessment is to accommodate that possibility within the budget planning. I understand why you might not want to let the project team see that figure, but that is irrelevant to the question that I asked. Did you take account of the risk in your management of the project? Why did you not report the potential cost to the minister who was responsible? Why was Treasury guidance ignored?
You are saying that it might have been prudent to have said that we were working to a £50 million target, but to have run the public finances on the basis that it might cost more.
Is not that what the Treasury asked you to do?
I do not think that that is the point of the Treasury guidance. The guidance is about saying, "We are going to build this for £50 million, but we might be beaten up to £70 million."Exhibit 18 in the report shows a graph that allows for the building cost estimate to rise; it doubles—whoosh. That is the problem with importing that aspect of the guidance at such an early stage. I understand that it works at a later stage, as I will ask John Gibbons to explain. It was not being ignored, but at the early stage of targeting, when people were driving hard to work to a certain figure, I am not sure that it would have been relevant to have said, "We don't really mean that figure."
Are you saying that a risk assessment should apply only when the risks are small and intangible, rather than at the start of a project when they are quite the opposite?
I will not say yes to that question. I would say that a risk assessment should not apply at that stage of such a project.
And the Treasury guidance?
It is guidance—the sort of thing that has to be tailored to meet the circumstances of particular projects at various stages. We would not ignore Treasury guidance. I would not say that my office would ignore Treasury guidance systematically; it will use such guidance maturely. It is important to understand how that is translated from the general to the particular.
On the Treasury guidance, there is a gap between theory and practice. We are aware of the guidance, which, as the permanent secretary has said, is just that—guidance. We have considered using the risk allowances as the Treasury suggests on other projects. It is very difficult to work in that way without encouraging inflation within the project. As soon as we identify a risk, we have to have the resources to deal with that risk.
You seem to be telling us that a risk assessment is an incentive to overrun on cost.
In theory, it is desirable to carry out a risk assessment. However, in practice, particularly in the public sector, where we disclose our accounting, what we set on one side as a risk allowance will become known to the design team fairly quickly and soon becomes the upper working limit. That is the difficulty that we have encountered when we have tried to translate the theory into practice.In this case, we chose to use the traditional method of a contingency followed by regular risk management exercises and a series of value engineering exercises in order to identify and manage the risks as we proceeded.
With respect, you are asking us to agree to the idea that Treasury guidance is inappropriate in this case and that it is an inappropriate policy approach because it encourages inflation in public sector projects, although it is designed to do the opposite. I find that bemusing.
All that I was saying is that that approach can cause inflation within the context of an individual project.
In that case, why does the guidance exist?
We have to develop a method to apply the guidance in practice. The new building was not a project on which we wanted to develop another bit of theory; it was a project that had to be delivered in a tight time scale and in the public arena. The theory on risk allowance has developed largely from the private sector, where there is greater flexibility in the approach to procurement.
I assume that you have written to the Treasury about your views on the inappropriateness of the guidelines, not just to this specific project, but in general.
The Treasury is well aware of the Scottish Executive's views on some of its guidance.
We are straying from the point slightly.
Annexe B of the Auditor General's report includes your minute to the First Minister, which explains that the project team had made the judgment that a number of risks that your cost consultants had included in their reports would not materialise. What advice had they received to support such a judgment?
That was the team's professional judgment. Those people work daily with designs and plans, talk to the design team, look at the brief and decide that the standard is already high enough, that high spec has already been designed in; and that we do not need some of the major risk allowances that are mentioned in the minute. For example, we do not need any art, as the art is the building. However, we need to take into account issues such as contingency. The project team makes those judgments as professionals, keeping their end of the wicket with the design team at the other end. Although I might be getting boring about this point, the matter comes back to the project team's aim to live within a budget. At the time, the team had accepted that the figure was moving from £50 million to £62 million; however, it had recommended that identified specific elements should not get into the frame, except to the extent that I have explained.Furthermore, I guess that other judgments that did not achieve such conspicuousness were being made all the time about something in a design, idea or a fax from Barcelona. That particular list of risks crystallised because the cost consultants, Davis Langdon & Everest, said that money should be provided for them in addition to the £62 million, and the project team said no. As paragraph 3.58 of the report makes clear, the risks did not materialise in the form that DLE identified. As a result, and with hindsight, it was right not to include those risks; and indeed it was probably a slightly isolated snapshot of a bigger process that was ongoing.
Given the professional advice that you had received, were you satisfied with that report to the First Minister?
Yes. Given the way that things had been handled, it was very important to be crystal clear for the public record that this had happened in the middle of activity between the design team and project team and had not broken out into First Minister world at all.
One of the cost consultants' risk allowances that the project team completely rejected was £5 million for delays during the handover to the SPCB. What was the rationale underpinning that judgment?
The rationale was that we were handing over the whole running show—the people on the project team who were fully familiar with the project. That risk allowance was recommended in case the team would have to stop and start one month along the chart, and the clear implication of ruling out such a recommendation is that that would not happen. When we come to discuss the handover, I will mention what was flowing through the system at that point, and nothing in the mechanics of the handover would have stopped anything. As it turned out, a quite different dimension of change was created. However, the cost consultants were not saying that the Parliament would redesign the project.
If I understand you correctly, there was a recommended £5 million allowance for a brief delay in the construction following handover, which you discounted, but there were no allowances for the client making any design changes.
That is correct. If the client wanted to make design changes, that would be a budget factor for the client.
Last week, the Auditor General said that he was concerned that"a firm cost plan has still not been agreed between all the main parties".—Official Report, Audit Committee, 19 September 2000; c 305.Has a firm cost plan been agreed; and, if not, are we not in danger of repeating the mistake referred to paragraph 3.52 of the Auditor General's report, in which he says—and excuse me for paraphrasing—that the Parliament might have been misled because the full costs of the project were not intimated to Parliament?
That question probably does not lie within Mr Russell's province. We have already established that there was no cost plan in place on handover, and I think that that is as far as Mr Russell's brief goes.
For my information, convener, who is currently responsible for a cost plan?
The responsibility now lies with the new client and, through it, Paul Grice as clerk to the Parliament and principal accounting officer of the Scottish Parliament.
I just wanted to know because it has been difficult to find out who knew what, when.
If you will just pause as we move on to discuss the status of the project on handover, we might explore the subject more fully.
There is a short answer to Ms MacDonald's question. Although I do not want to transgress on Paul Grice's area and the ground that you will cover with him, I understand that there is a definitive cost plan reflecting the stage D that the changed design has now reached.
Thank you. I want to move on to the next stage, which is the status of the project in June 1999 at the point when responsibility for the project was transferred to the SPCB.
I do not know whether Andrew Wilson set a bad example, but I will follow him and start with a question on the previous matter. Throughout this evidence-taking session, cost and time pressures have been mentioned as reasons why you used certain processes for the management and cost reporting of the contract. Do you accept that, as the project is outside the budget and the deadline, those processes actually failed?
I agree that the processes did not deliver a project for £50 million and that it was right to amend and increase aspects of the brief, with associated cost drives. Beyond that, "failed" is a big word to use to describe an evolving process. You will understand if I do not agree with the use of that word. The outcome was different in a number of what I believe are explicable and justifiable respects. We have got into semantics now—I am sorry.
Given that much of what we have covered so far is to do with the process of how the situation was arrived at, and given that you have dismissed the alternatives that were suggested by the Auditor General for Scotland, have you an idea of how you would tackle the matter now? Dr Gibbons said that lessons were to be learnt from the process. Would you use the process for another major project, or would you use an alternative?
That is a difficult question. I am not sure that the Auditor General for Scotland is offering you a set of prescriptions that he thinks would definitively have made a great difference. I am not sure that he is doing more than answering what he described as quite tentative questions. With regard to his comments on the project management expertise, I am not sure that he has made the linkage between his risk graph and the outcome as I have explained it. There are wee gaps between the Auditor General for Scotland's comments, which are about aspects of process as defined in guidance, some of which is dated 1999, which means that it came after we had started on the project and is not relevant to the reality of what we were trying to do. That does not mean that everything that we did is perfect. I am quite sure that you will find moments in the exchanges between the project team and the design team when a design issue could have crystallised or when something could have been done more cheaply or quickly. However, I do not think that the processes that we have been talking about today would have helped that. I do not see the cause-and-effect links in the report. Valid as the suggested alternatives might have been for other projects, I do not think that they would have been suitable for the project that we were involved with. Obviously, there has been much to learn and think about that could be applied were we ever to embark on a similar project. I do not want to give the impression that we would not study this report before embarking on such a project, but I do not see it as obvious that the points in the report would have made a difference to the project at that stage, given the conceptual elements that were involved.
Mr Black was at great pains to indicate to us that he had some questions. Perhaps you might care to offer your view of what the answers should be—perhaps not immediately, but after having had some time to consider the issue further. Perhaps Dr Gibbons could tell us what lessons could be learned from what has happened—again, that could be done at a later date.In order to satisfy the convener, I will move on to the next point.
If we could at least get the train out of the station, Mr Adam.
The report says that, when the project was transferred to the Scottish Parliamentary Corporate Body in June 1999, there should have been an independent review. What evidence did you have about the health of the project immediately prior to transfer?
We must think of what it was that was handed over. It was a project that had been subject to all the processes that I have talked about, going right back to the setting of the target figure and the one-year consultation on the brief in the real world. The process had built and developed the design during that time and, after a lot of huffing and puffing and reluctance on the part of the team, it had been agreed that there were some increases that should go in and were perfectly well justified. By that time, the concept was pretty firm and contained the elements of a pretty good building in terms of design and the capacity to deliver what was wanted, according to the brief as adjusted. So the design was credible. Then the question is, were the budget, expectations and timing credible? There was a thick stage D document ready in draft. Still to be tidied up were checks of area, detailed room adjacencies—things like that. At that stage, the project had been designed to the point of being put in for planning permission and historic buildings approval and it had the support of Historic Scotland. There was a lot about it that was pretty firm and credible. That is why I think the project was viable and in good health when it was handed over. You may say that there was a cost element—as discussed already, £25 million or £27 million—but we have dealt with that. All that leads me to believe that the project as handed over was credible, buildable, well described, properly priced and an entirely reasonable project to hand over to the SPCB for it to take forward as it wished. The SPCB's response to the Spencely report was that it may well have been possible for the project as it then stood to have been completed for around £109 million. Again, that has not really been challenged. Subsequently, as I understand it, the project team was able to accept the stage D report within a few weeks of the June date. The team was able to drive on and do value engineering, as we had envisaged. As the report shows, that released the potential for about £20 million of cost savings. That gave some comfort on deliverability for the costs that were being mentioned. In my view, for those reasons, it was a respectable, credible project at the handover.
I know that you listened to Mr Black's evidence earlier. I asked him, in relation to the statement that he made to us last week, whether he would clarify where and when in the process the additional specifications that led to some of the additional costs came in. He said that he was not sure whether he could differentiate between what was before and what after the handover. Will you or your colleagues give us guidance on how much of the 47 per cent additional costs due to enhanced specifications was as a consequence of decisions, thoughts or discussions prior to the handover and how much after the handover?
There was a lot of redesign work as a consequence of a decision to revisit the shape of the chamber. Somewhere we are told that 75 per cent or 80 per cent of the design work had to be redone as a result of that and the other changes that were—
That is one element of it, but it might be helpful if you could write to us about that. It is a detailed technical point. Would it be reasonable to ask you to do that in a fairly short time scale?
Can I make sure that I fully understand the question? The report says that 50 per cent of the cost increase was due to size factors, and that 50 per cent, give or take, was due to quality—or rather area and quality. You would like me to say how much of that rise in the construction costs from £50 million to £108 million was included in the £62 million and how much came later. You are asking whether that was to do with area or quality.
I am not just referring to the amount of the increase taken into account for the £62 million figure, as there must be some doubts about that figure. How much of the increase was because of processes, discussions and decisions? How much of that was before the handover of the project to the SPCB and how much of it was post-handover?
We will do our best to answer that. Remember that the £62 million contained a DLE estimate. The base estimate was DLE, and there was then an extra figure.
I know that there was another £6 million in contingencies.
There is a lot of firmness around the £62 million figure. I am very happy to try to answer that question for you, Mr Adam, and we obviously want to do that fairly quickly. The question of what happened over the cusp is something that you might also have questions about.
Yes, I would appreciate that. It was not until June this year that the project management, the cost consultants, the design team and the construction manager were able broadly to agree on the expected total construction costs of the project. Why did that not happen before the transfer to the corporate body in June 1999? Exhibit 18, the graph on page 41 of the report, shows the consistent gap between the different figures for the estimated expenditure, and the figures only come together at a later stage, this year.
The process that would have ensued in June and July 1999, if the decision had simply been to continue with the handover, would have closed that gap fairly quickly. Manifestly, the £25 million or £27 million would not have been included, stage D would have been ready and some of the issues that were subsequently opened up would not have been opened up. Planning permission was about to come through. The figures were on a convergence course—and that is the difference. Perfectly legitimately, for reasons that I do not remotely want to challenge, the members of the Parliament decided that they would consider other options, and that led in different directions.The team, given its degree of impetus and commitment, and given the stage that it had reached, would have closed down the gap between the different estimates fairly quickly. We could argue back and forth about the validity of anything that was done subsequently, but that is my judgment, based on what we handed over and on what had gone before. The estimates were not just pulled out of a hat; they were the result of what had become quite a big process by that stage.
I notice that you used the phrase "closed down". In reality, the gap between the two estimates was closed up, was it not? By that I mean that the figure which was budgeted for had to increase in order to meet the figure that had been suggested by the cost consultants. In fact, it got very close to the cost consultants' figure, which had been in existence for several months.
You will have to ask the people who have formal responsibility for that.
Yes, but my point is that the gap between the different figures was always there. At the time when the figures closed together, if I may phrase it that way, it happened to be under someone else's responsibility. However, the gap was consistent throughout.
Do not forget the value of engineering, the £20 million. Most of that was lost because, in the mêlée of redesign, the savings could not then be delivered. It is a dynamic situation, and you have to remember that, once the constraints are taken off, a lot of different things run in.
Can I ask—
No, sorry. I want to bring in Euan Robson first.
For the sake of clarity, I refer you to annexe B, paragraph 1, in which you say:"The First Minister was not made aware of the existence of the higher figure"of £89.2 million, which, as the annexe says, was quoted in the Spencely report. Was the corporate body—or those to whom the project was handed over—also not informed of that figure?
I cannot tell you what the project team then did in relation to the corporate body in terms of indicating any aspects of the back history. Given that the team had made the judgment that those things were not going to happen, I suspect that that is right, but I am guessing. I have not asked.
Why did you not insist on a firm design before the transfer to the SPCB? Was it not originally intended that there should be a firm design?
Yes, it was.
Coming back to my question about cost transfer, why did you not insist on a firm design, so that you could at least give a baseline to the SPCB for any changes that it might want to make?
The transfer date was set in statute. People were doing their best to work towards it. I know that it was not a firm design, because stage D was not complete. The information that I have is that it was a few weeks away. It was substantially complete; there were a few details to deal with to complete it. I have given you the other elements of context that suggest to me that the design was firm and was being reacted to by planning authorities and others. People were working very hard. They missed the date by a few weeks, but the numbers that they had for the cost were robust in terms of what stage D was going to show.The statutory date came upon us. The job had to be done; the handover had to be made. The First Minister was given the best advice that we could give him and he made a statement explaining that the project, looking as it did, would cost a certain amount and that there was a budget for it. In an ideal world, it would have been nice if all that had happened just a little bit earlier, but it could not. We had the business of getting the architects and the team together to sort out those last few things. It was damned hard going, and that is why.
One of the areas of potential risk identified in the report is the recommended £5 million allowance for the handover. That struck me as rather odd, as it was broadly the same project team before and after the handover. Where was the big risk?
Precisely. That was the judgment that members of the project team also made—that is why they knocked it out.
We now know that the project ran into difficulties in August 1999, about three months after the SPCB became responsible. How many of the points in paragraph 1.18 on page 12 of the Auditor General's report do you think arose from the Executive's period of stewardship? In particular, I would like to get back to the business of the design element, as it seems that the design team designed the chamber to a design that did not meet with universal approval—that is an understatement—when it came before MSPs.What sort of consultation had taken place when you were in charge of the project on issues such as the design and shape of the chamber? Were those things imposed by the architect? Was it only when things came to open, bloody rebellion that they were redesigned? If so, would an earlier period of consultation have resulted in rather lower costs at a later stage? Redesigning the chamber meant redesigning the site, as I understand it, to allow circulation areas and other changes that impinged on other aspects of the design.
I could make the rather jejune point that there were no MSPs until May 1999, but there was a process of consultation, which Robert Gordon and John Gibbons can explain.
There were public exhibitions of the emerging proposals and people had an opportunity to comment on them. There had been consultations with the political parties on the design brief. The design team was picking up the language from the consultative steering group, to get a feel for what kind of Parliament this was going to be. For example, one of the objectives was to avoid the adversarial nature of the chamber in Westminster, and the architect had come up with a shape to achieve that. Ministers were not inclined to impose a view on the design at that stage.
We had developed a well-detailed brief on the basis of a series of desk appraisals of modern parliamentary designs and the consultation process that Robert Gordon mentioned. The design, in what we call the not-quite-finalised stage D, fully met the requirements of that brief, so the architect had not in any way strayed from what he had been asked to do. At that time, the concern that you have referred to was emerging: some MSPs were not entirely enamoured of the idea of a banana-shaped chamber, as I think it was described at the time.
That was one of the descriptions that was applied to it.
I would like to be clearer about some of the answers that have been given to Mr Adam and to you, convener. Looking at the various items in the Spencely report for stage D at the end of May, we see such headings as "Enhancement" and "Contingencies & Design Reserve". You did not think that the risk of change to those items was alive before handover. However, within 12 weeks, all but one of the figures has considerably increased. The Auditor General was clear that, in his view, not a great deal had changed during that 12-week period to have brought the increases about. However, you have said that they were all due to changes in that 12-week period. As Lord James said, both views cannot prevail. How are we to make a judgment? Whom do we trust? Can we have more of an explanation?
If Mr Wilson will allow me just a second, I will try to decode some numbers from Spencely.The table that I am looking at on page 8 of the Spencely report attributes a huge hunk of the difference between the "Stage D" number and the "Interim Cost" number at end August to the chamber change. Much smaller amounts are attributed to things that are called "Design risk Assessment" or "Contingencies & Design Reserve". I would like to go away and have a look at this, because this quick look at the numbers could provide a basis for answering the question about what happened—on, almost literally, the day of the handover—that shook the thing off the rails. I will come back to Mr Wilson on that.
Okay.
I heard the Auditor General suggesting that, if I may put it crudely, things could not have been all that well with what was handed over if so much changed so quickly. Mr Wilson has made that point too. The other view is that specific things were changed that accounted for the differences. If that is the case, it is only fair that members should know about it. My gut feeling is that the latter view is correct, but I will need to analyse these numbers to help Mr Wilson with that.
That would be helpful.
I will do that by next week, when you are seeing Paul Grice.
I asked a question about paragraph 1.18 of the Auditor General's report. We have acknowledged that there were no MSPs to be awkward before the Parliament first assembled, but what about the other elements in paragraph 1.18? Which ones were in your control and affected the project after it was handed over to the SPCB?
My clear impression is that the process that I described, with much hand waving and words like "closed down", did in fact change quite dramatically, instantly, in terms of where resources were going. People were travelling, looking at different design possibilities, and they were not closing it down, but were into a different ball game.I think that is why the dynamic that would have led to the agreement between the design team and the project management—the last bullet point on page 13—which would have led to the construction information continuing—the second last bullet point—which would have delivered that crisp stage D and everything that goes with that—the third last bullet point—really slacked off, for perfectly understandable reasons. I am disinclined to believe that those bullet points, valid though they may be as statements of what happened, reflect a fatal weakness in what was handed over, as distinct from a dependence in what was handed over on the process continuing to that closedown. I keep using that word, I apologise. That is my answer in relation to that set of bullet points.When people started looking at design-related issues that were coming up, there began to be quite big uncertainties. Once they started stirring the shapes around, measuring what they were and what the associated costs would be got difficult. That explains the second bullet point on page 13. Similarly, once they started looking at things affecting Queensberry House garden and the like, that led to a whole new ball game with Historic Scotland.Looking at the first three bullet points, I think that pulling quite a little thread pulled an awful lot of the pattern. As you can see from the comment about 70 or 80 per cent of the design having to be redone, in a project like this elements that are easy to describe produce quite a big change in the work, in estimating and costing. I think that it is reasonable to sustain my position that the design was set to go though and work, but that things that were very big in their impact came along very quickly—right then, bang, in June—and changed the dynamic of what people were doing. All their energies were thrown in different directions and they had to look at the ramifications.
I think that there are distinct possibilities of overlap on this issue between you and the other accountable officer. I am sure that Paul Grice's views will also be taken into account. We may want to return to that in the future.We are drawing to a close, but I should go back to Paul Martin, who has one more question on cost reporting.
In Mr Black's report Mr Russell points out that the cost reporting was unsystematic and did not give equal emphasis to different aspects. Why did you not make sure that all the relevant cost information was reported up the line on a regular and consistent basis?
What was being targeted was in the public eye. The headline number was the construction cost; that was the thing you could find all the way through. At various times, as things began to crystallise, other elements entered into the information as people were able to give it. The central thing was the construction cost, which was systematically reported on. As I say, when other elements were settled and people began to get a handle on the associated costs, they emerged into the public domain as well.In terms of regular reporting, it all comes back to the fact that it was not the sort of project that was following a standard little plan. Robert Black talked about buying a garage, but the project was so different to anything that one would usually conceive that we did not intuitively expect a report on the third Thursday of every month that said how things were going in the discussions between the project team, RMJM and the Barcelona people. There were moments of quiet, when people were away working and drawing, and then there were great bursts of activity, when people costed the proposals and went back to the brief. It was bound to be a very bumpy process.Given the intensity of effort, negotiation and creativity that was going into the project, I would forgive people for not sitting down on the third Thursday of every month to write a report. That does not mean that people took their eye off the ball when it came to reviewing the key figure, both within the team and when they were ready to report to the secretary of state. That is half an answer—it is what I think was happening. It does not imply that people were not doing their job or not working as hard as they could to deliver on target.
I would like a yes or no answer. In paragraph 3.51, Mr Black points out that the reports were"not regular and systematic in relation to the total costs of the project".Do you agree with that statement?
They were systematic in relation to construction costs. At various times, reports included elements such as fitting out costs—that is what the Auditor General is referring to when he talks about estimating fees, furniture and VAT. Some reports included those costs and others focused on the central construction cost. I am content to put up my hand and say that the Auditor General is right on that point. He has seen the documents; I would not say that he cannot read.
I thank Mr Russell, Dr Gibbons and Mr Gordon. I would like to remind you what we have agreed this afternoon. You will provide: notes on the degree of practical experience of construction management projects in the project team; details of the job specification for the replacement project manager and the method of his recruitment; an outline of the general lessons that the Executive has learned from its involvement in the construction of the new Parliament—I look forward to that one—and a note on the proportions of the increase in construction costs that are attributable pre and post-handover.Thank you again for appearing before the committee. I have no doubt that we will talk again in the near future.
On behalf of my colleagues and myself, I thank members for the courtesy that they have shown and the mature way in which the debate has been conducted. If the committee needs further information about the project during the time that it was in my stewardship, I will be very happy—perhaps that is the wrong word, I should say "prepared"—to offer any help that I can, in the form of written or oral evidence as the committee wishes.
Meeting continued in private until 17:30.
In this meeting
Everything on 26 Sep 2000 →- Scottish Parliament Audit Committee Tuesday 26 September 2000 (Afternoon) Committee business · 2
- Holyrood Project Committee business · 292
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.