Andrew Welsh SNP Angus
link

We cannot run the Scottish civil service, but we can encourage best practice and point out faults and failings—that is what the committee is all about. We are fortunate to have Audit Scotland to give us detailed back-up and information on which we can base judgments. Our job is to encourage best practice in the Government machine, not to run it.

Andrew Welsh SNP Angus
link

We have always encouraged best business practice. One of the great strengths of Audit Scotland is that it promotes good common sense and sound and solid management. Where that approach has been adopted by those reported on, there has been an immediate positive effect. We can make recommendations and encourage good governance.

Andrew Welsh SNP Angus
link

The chief civil servant is not a project manager. He cannot be expected to wander around every project in welly boots. We are talking about an early-warning mechanism and data and information gathering regarding progress—or, more important, lack of progress—in projects. It is about how the Government and ministers are alerted so that action can be taken. Sir John Elvidge wrote:"I believe I was first advised of potential cost overruns on the Stirling-Alloa-Kincardine rail project in the Autumn of 2007, in conversation with the Director General Economy. I satisfied myself that the relevant Director General … and the Chief Executive of Transport Scotland were taking the necessary action to manage these risks, in concert with the Project Board."It all comes down to how he satisfied himself, as he puts it. That could well have been in writing, or other methods could have been used. He has been entirely honest with us in his answer. Our real question is how good and efficient the early-warning mechanism for projects is, and how it can go wrong.

  1. Scottish Parliament Audit Committee Wednesday 26 November 2008 Committee business · 1
  2. Decision on Taking Business in Private Procedure · 1
  3. Section 23 Report Committee business · 72
  4. Section 22 Report Committee business · 6
  5. Section 23 Report: Response Committee business · 18

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.