To ask the Scottish Government whether it will provide an update on the progress of the A720 Sheriffhall roundabout project. (S6O-04760)
Official Report · Chamber
General Question Time
link
To ask the Scottish Government whether it will provide an update on the progress of the A720 Sheriffhall roundabout project. (S6O-04760)
We continue to progress the proposed improvements at Sheriffhall through the statutory process. Given the large number of objections received following publication of the draft orders, a public local inquiry was held between 31 January and 8 February 2023. The independent reporter’s conclusions and recommendations have been submitted to the Scottish Government and are under active consideration prior to advice being provided to Scottish ministers, who will then decide whether the statutory process should be completed.
link
It is coming up to two years since the independent reporter submitted her conclusions to ministers. Can the cabinet secretary confirm whether the money allocated previously is still ring fenced and, given cost inflation, whether it is still adequate to meet the construction costs?
I assure Colin Beattie that the Government remains committed to the Edinburgh and south-east Scotland city region deal, which includes up to £120 million for grade separation at Sheriffhall roundabout. The financial risk for any cost over and above that figure lies with Scottish ministers.
As is the case for all other road infrastructure projects, the cost estimate will be updated once the statutory process has been completed and in advance of procurement. Funding to progress the construction stage will be determined as part of the annual Scottish budget-setting exercises.
link
This week, I launched a campaign so that people across Lothian can make their voices heard about this notorious junction. After 20 years of discussion and the spending of more than £6 million on consultation fees, we are no further forward. Motorists across Lothian have had enough of the delays. Can the cabinet secretary confirm that the project will be given the green light before the next Scottish Parliament election?
Although we are keen to see the improvements being delivered as soon as possible, the statutory right for individuals to have their say on proposals cannot be set aside. I am sure that the Conservatives would want the statutory processes for a number of projects to be concluded quickly. In this case, I have yet to receive the advice on the reporter’s recommendations, but the timetable for decision making and dealing with any implications for the budget process can be made thereafter.
I am not surprised that Miles Briggs has launched such a campaign—had he not, I would probably have done so myself. My constituents in the Borders and Midlothian have to use that junction all the time—as do I, because it connects to the A68 and the A7 in my constituency. I add my own concerns about the delay to the project going ahead, because it will only become more costly the longer that the delay continues.
I acknowledge the concerns raised by Christine Grahame and other members. The proposed new flyover arrangement at Sheriffhall would separate local traffic, including public transport, from strategic traffic on the Edinburgh city bypass. It would improve traffic flow on the bypass at that location, which would in turn improve road safety and journey times for users. In addition, the proposed new active travel facilities would provide cyclists and pedestrians with their own safer, dedicated alternative routes, by removing the existing barrier and transforming the way across the A720.
However, I remind members that 2,773 objections to the proposals were received. Advice on the matter will come to me once the Scottish Government has completed its analysis of the reporter’s recommendations. Although we have received those, I have yet to receive the subsequent advice. When I receive that, I will deal with it.
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.