New Petitions

Energy Infrastructure Projects (Public Consultation) (PE2095)

Wednesday 11 September 2024 Citizen Participation and Public Petitions Committee About 10:15 Petitions 14 contributions · 4 speakers

Speakers

Choose an MSP to read only their contributions

The record

14 contributions
Jackson Carlaw Con The Convener · Eastwood
link

Our next new petition, PE2095, which was lodged by Margaret Tracey Smith, calls on the Scottish Parliament to urge the Scottish Government to review and seek to update section 3.2 of the energy consents unit’s “Good Practice Guidance for Applications under Section 36 and 37 of the Electricity Act 1989”—that was a mouthful—to address the concerns of communities about the lack of meaningful, responsible and robust voluntary and pre-application consultation by transmission operators on energy infrastructure projects, and to explore all available levers to strengthen community liaison and public participation for the life cycle of energy infrastructure projects.

We are joined for our consideration of the petition by another of our colleagues, Tess White, who is a former member of the committee. Good morning, Tess.

The petition has been prompted by concerns about the quality and transparency of the public consultation accompanying SSEN Transmission’s east coast 400kV upgrade project, which the petition has described as rushed and inconsistent.

The SPICe briefing highlights that there are no statutory pre-application consultation requirements for energy consent applications under sections 36 and 37 of the Electricity Act 1989. Instead, the carrying out of pre-application consultation with the public is considered good practice, with the Scottish Government’s energy consents unit having published guidance on what that should include.

In responding to the petition, the then Minister for Climate Action told us that, although the Scottish Government has made repeated requests of the United Kingdom Government for additional regulatory powers to place pre-application engagement on a statutory footing, electricity transmission remains a reserved matter. The minister also stated that, although current good practice guidance is considered appropriate for most forms of electricity development, the scale and linear nature of transmission development potentially requires a more detailed approach to be set out in guidance. The response went on to say that Scottish ministers will consider how to take forward development of pre-application guidance specific to transmission line applications, with the intention of giving affected communities clear and meaningful opportunities to influence the process of developing route options.

There is some interest in progressing some of the aims of the petition, which I think is significant, but, before we proceed to comment further, I ask Tess White whether she would like to speak to the committee.

Tess White Con North East Scotland
link

I thank the Citizen Participation and Public Petitions Committee for its consideration of PE2095. I also pay tribute to Margaret Tracey Smith, the petitioner and co-founder of the campaign group Save Our Mearns, who is here today.

As a North East Scotland MSP, I have received more correspondence on SSEN’s plan for a new 400kv pylon route from Kintore to Tealing than on any other issue. SSEN’s consultation has been described as pitifully wanting and engagement events as box-ticking exercises. Residents have repeatedly red-flagged incorrect information. Entire communities feel disenfranchised and distrusting of a process that seems like a done deal. However, at issue is not just the way in which SSEN has conducted the consultation. This is also about consultation as part of the consenting process for new transmission infrastructure, which we know is set to increase dramatically in the coming years.

Affected communities do not believe that the Scottish Government is listening. Ministers have been paying lip service to the importance of communities in policy making, but my constituents have felt sidelined and ignored. As the Net Zero, Energy and Transport Committee emphasised in its report, Scotland’s electricity infrastructure planning and consents law is almost entirely devolved. However, an important point is that the Scottish Government has the levers it needs to act.

Gillian Martin, in her then role as Minister for Climate Action, responded to the petition. In that, she acknowledged that there is a problem. However, the proposed solution to give communities opportunities

“to influence the process of developing route options”

falls well short of what is needed. What about influencing alternatives to overhead lines, such as underground cables? What does meaningful consultation look like? Crucially, what will be the consequences for transmission operators who fail to follow the updated guidance? We need more detail on what the Scottish Government is proposing. I urge Scottish ministers to have formal community involvement, such as through a working group, as it formulates and implements the necessary changes.

Finally, there was an important debate on SSEN’s proposed pylon pathway. Sadly, that was a members’ business debate; it should have been a full debate in the Scottish Parliament. Fergus Ewing MSP, who sits on the committee and is here today, suggested that the Scottish Government should dedicate time to hold a full parliamentary debate. That proposal needs to be revisited and parliamentary time should be allocated to doing so as soon as possible.

For my north-east constituents, this is far from a just transition. Their voices must be heard, and the system must change.

Jackson Carlaw Con The Convener · Eastwood
link

Thank you very much, Tess. The petition raises significant issues. I am sure that the committee will wish to keep it open. Do colleagues have any suggestions about what we might do?

Maurice Golden Con North East Scotland
link

The timetabling of debates is a matter for the Parliamentary Bureau to discuss, and I am sure that the member can discuss the matter of ensuring that the topic is debated in Parliament with her business manager.

There are several aspects that we need to unpack. Several different actors are involved in energy infrastructure, and it would be useful to get opinions from them.

First, on the Scottish Government’s position, it would be useful to understand what discussions and engagement it has had with the UK Government on regulatory powers that would put pre-application engagement for electricity transmission on a statutory footing.

Jackson Carlaw Con The Convener · Eastwood
link

On that point, I note that the Scottish Government has said that it has made repeated representations. It might be useful to ask for a schedule of those representations so that we can see when all those repeated representations have been made.

Maurice Golden Con North East Scotland
link

In addition, it would be useful to know what the Scottish Government’s position is on pre-application engagement. My understanding is that—it would be useful to have clarification on this point—pre-application engagement could reduce public participation and make it easier for energy infrastructure to be rolled out without community involvement, but I stand to be corrected on that.

It would also be useful to get the Scottish Government to outline how it sees public participation with regard to decision making in that area and, ultimately, to understand how it considers that that could be improved. That links to the second bullet point in the petition, which is about community liaison and public participation. That is where that aspect gets quite complicated.

The UK Government has a role in providing licence conditions for the Office of Gas and Electricity Markets, so we should get a position from it as the energy regulator. We should also get a position from the national energy systems operator on how it might highlight the current Kintore to Tealing infrastructure and infrastructure that might be required in future in that place. I think that it has a role in highlighting future infrastructure. There is also a role, as we have heard, for the transmission operators and, potentially, for the distribution network operators, who might be doing smaller-scale energy infrastructure.

There is quite a lot to understand in how all this pieces together. A member of a community might not fully appreciate all the different stakeholders that are involved in delivering energy infrastructure.

Fergus Ewing SNP Inverness and Nairn
link

I have some sympathy with what the petitioner has said. This is not an easy topic at all. I will start by making the point that the pre-application process is essential. Once things get to the stage of formal application, the developer will have spent an enormous amount of money on setting out a very detailed scheme; that process can be very costly. There will be an in-built reluctance to depart from that scheme after it has got to that stage. Therefore, it makes sense that pre-application stage is where the real effort on consultation should be made. Moreover, as I understand it, that approach is taken towards large planning applications. It would be inconsistent if that approach did not apply to energy.

Secondly, there is now a new UK Government, and the Scottish and UK Governments are aligned in saying that renewables are a great hope for the economy and for energy. If I set aside whether that is right or wrong, there is a confluence of objectives.

Close consideration needs to be given to how we persuade people that their views are being taken seriously. The SPICe briefing says, for example, that the pre-application guidance states that seven days’ notice must be given of consultation meetings. That period is hopelessly inadequate. Many people will simply not be able to change plans that they have made in order to attend in seven days, or even hear about the consultation meetings or see that in the newspapers. That is a common complaint.

I do not know the situation that Tess White has alluded to in the north-east as I am not familiar with the details, but I know that, in the Highlands—according to Graham Barn, the spokesman for the Civil Engineering Contractors Association Scotland, who gave evidence to the committee on another matter—that there is £45 billion of grid-strengthening work in the SSEN area alone between now and 2035. That is unprecedented, and it will involve substations at places such as Kiltarlity and Broadford, which have attracted huge controversy. Therefore, unless the process is one that enjoys the confidence of people, the Scottish and UK Governments will be storing up problems unless they give serious consideration to that.

My last two points are about the related issue of what benefits local communities get. Unless they get cheaper electricity, there will be sour, rumbling, protracted discontent. Both Governments need to consider how the areas that take the flak and get the infrastructure, receive some benefit directly, whether that be in lower electricity costs or in community ownership, or both.

Lastly, I agree with Maurice Golden that the committee does not have the power to say what Parliament should debate—it is a shame that we do not, because things might have gone a bit better if we did. Laughter. That is just my humble opinion, and who is going to listen to that? However, why are we not debating this topic? It is a live issue. Tess White has brought it here today, but a whole suite of MSPs, if that is the right collective noun, are affected, and there is huge concern across Scottish communities about where the turbines and the substations will be. The rest of Scotland may well be absolutely supportive of renewable energy, but it is not bearing the brunt of things.

I am very pleased that the petition has been raised and that Tess White has addressed us today. The interests of other MSPs are noted. I hope that the Scottish Government and the UK Government will take all those things into account.

I am sorry, convener, that that was a bit long.

10:15

Jackson Carlaw Con The Convener · Eastwood
link

Your comments are very much appreciated. I believe that the correct term is a parliament of owls, not a suite of MSPs.

Jackson Carlaw Con The Convener · Eastwood
link

If we have all the wisest owls here, Mr Ewing, we can be very pleased with ourselves.

I think that I caught one or two suggestions in Tess White’s evidence—that will be in the Official Report. There was something about underground cabling. Could you repeat that little section for me?

Tess White Con North East Scotland
link

Those were about undergrounding and offshoring. I can send my notes, convener. My suggestion was to do with influencing alternatives to overhead headlines such as underground cables. There is also offshoring to consider.

Jackson Carlaw Con The Convener · Eastwood
link

I am happy to include that in any representation that we make.

We have had quite a collection of suggestions. Are colleagues content that we keep the petition open, and that the clerks work out what colleagues recommended in that detailed list of submissions?

Members indicated agreement.

Jackson Carlaw Con The Convener · Eastwood
link

We thank the petitioner very much. I hope that she been pleased to see the interest that the committee has in her petition. We will take forward the aims of the petition, and we will see what progress we are able to make with it.

  1. 09:30 Decision on Taking Business in Private Procedure · 1
  2. 09:30 Continued Petitions Petitions · 4
  3. 09:30 Continued Petitions Petitions · 6
  4. 09:45 Continued Petitions Petitions · 9
  5. 09:45 Continued Petitions Petitions · 4
  6. 09:45 Continued Petitions Petitions · 3
  7. 09:45 Continued Petitions Petitions · 3
  8. 09:45 Continued Petitions Petitions · 3
  9. 10:00 New Petitions Petitions · 3
  10. 10:15 New Petitions Petitions · 14
  11. 10:15 New Petitions Petitions · 3
  12. 10:15 New Petitions Petitions · 16

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.