PE1931, lodged by Ian Barker, calls on the Scottish Government to prevent the digital exclusion of rural properties and households by giving priority in the reaching 100 per cent—R100—programme to properties with internet speeds of less than 5 megabits per second.
At our previous consideration of the petition, the committee agreed to write to the Scottish Government and the relevant contractor—BT Openreach—to seek further information about how work is sequenced and prioritised. The Scottish Government’s response explained that it conducted an open market review to identify the premises that would be eligible for public investment through R100. The intervention area identified was tested through a public consultation to confirm that it was accurate. The Scottish Government also weighted the scoring for some rural locations as part of the bidding process to encourage deployment in those areas. The submission provides information about the full fibre charter for Scotland, which aims to extend build further into remote, rural and geographically challenging areas.
BT Openreach’s response to the committee explains its inside-out approach to sequencing works, whereby build begins from the primary exchange location, where the main fibre controls unit is located, out into the communities. The rationale for that is to make the most use of public subsidy and extend the network as much as it can with the funding that is available.
Finally, a recent parliamentary question from Willie Rennie MSP highlighted an FOI that, he said, reveals that the full R100 programme will not be delivered until March 2028.
The subject has entertained the chamber with a degree of controversy for as long, frankly, as I can recall. Colleagues, have we any comments in the light of the evidence that we have received?