Thank you for letting me make an opening statement to explain what has been a difficult and unquestionably controversial decision, but a necessary one. Before I make that statement, I reiterate, if I may, my apology to 800 seafarers and their families and, specifically for this committee, to the 39 affected seafarers and their families who live in Scotland.
The backdrop is that P&O has lost an unsustainable amount of money in the past few years and has not been viable or competitive for a number of years. Without a material change to the business, I would not be here answering questions about the loss of hundreds of jobs, as difficult as that is; I would be here talking about the loss of thousands of jobs, because if we had not made material changes to the business we would have had to close it.
The business has been funded to the tune of hundreds of millions of pounds by our shareholder, who has never—not once—taken a dividend from the business. It is not sustainable. It is not possible to expect a shareholder to unconditionally and indefinitely support a business that has no plans to change. Sadly, we had to bring about significant change. At the core of that was the very difficult decision to change our operating model.
I do not think that I have fully explained why that change to our operating model is so material. I would like to take time to do that. The vast majority of the impact of the decision is on the Dover to Calais route and is better explained with reference to that. We used to operate and pay for four full-time crews, which, in reality, was more like 4.8 crews when we accounted for sickness and training. We had to pay for four full-time crews who worked for 24 weeks a year.
The new model is a different way of doing business. We are outsourcing our crewing arrangements. By doing that, we will be paying for only two crews and paying only when they work. That gives us significant savings and an increased level of flexibility, so that we can compete. That model is radically different from where we were but is recognised and used in 80 per cent of shipping across the globe, and is one that the cruise industry moved to decades ago.
Having made that very difficult decision about our model, there were reasons why we implemented the decision in the way that we did. We assessed all the available options. Ultimately, we as a board and I as the chief executive concluded that implementing the model in any other way than by the route that we chose would lead to the closure of the business and the loss of thousands of jobs rather than, very sadly, hundreds. Because that critical decision was so radical, it was our conclusion that no trade union could possibly accept our proposal and therefore that any consultation would frankly have been a sham.
We are, of course, compensating people as we are required to, in full and up front, for the failure to consult. On top of that, we are overlaying a significant redundancy package, which we believe to be the largest such package issued in maritime history. There has been a lot of talk about how big that package is for staff at the top end, but I think that what is most important is that, although we did not cap the top, we capped the bottom. That means that, for the people who are less well-paid and who have been with us for a shorter period and who would normally have received a much smaller payment, we capped the minimum payment at £15,000. Where we sit today, 765 out of 786 seafarers have started the process to accept that, and we will support the remaining 20-ish seafarers if they need any support to make their decision about whether to accept our offer.
I have just one last thing to say. We now move to two priorities. The first is finding new jobs for those 800 seafarers. We have engaged a number of organisations to do that, and it is a clear objective of ours. The second is to restart our business. With reference to this committee, that means particularly the Larne to Cairnryan service, which I would like to bring back safely to a full schedule to deliver the trade requirements for the route between Scotland and Northern Ireland.