Our last new petition is PE1916, which requests a public inquiry into the management of the Rest and Be Thankful project and was lodged by Councillor Douglas Philand and Councillor Donald Kelly.
As promised, I am delighted to welcome back Rhoda Grant for the final petition this morning. I will come to her shortly.
The petition calls on the Scottish Parliament to urge the Scottish Government to instigate a public inquiry regarding the political and financial management of the A83 Rest and Be Thankful project, which is to provide a permanent solution for the route.
Transport Scotland explains in its submission that, following a number of landslides across Scotland in 2004, a nationwide Scottish road network landslides study was carried out. The study concluded that the A83 Ardgartan to Rest and Be Thankful is one of the most highly ranked debris flow hazard sites in Scotland.
In 2012, Transport Scotland commissioned a study to identify and appraise potential options to minimise the effects of road closures. The final A83 route study, which was published in February 2013, explains that the decision was made to progress with the red option, as it was considered at that time to offer the best performance and the most cost-effective way of meeting the study’s objectives. Those objectives included maintaining the existing alignment of the A83 with a range of landslide mitigation measures such as additional debris flow barriers at locations where the landslide hazard was considered highest; the improvement of hillside drainage adjacent to and under the road; and the introduction of vegetation and planting on the slope.
In its submission, Transport Scotland provided a range of data that shows the number of days on which the various stretches of road in and around the A83 were closed due to landslides. The data shows that the events that occurred in 2020 and 2021 were significantly larger in scale than any of the previous events.
Following that, several new measures were introduced to make it quicker, easier and safer to open the road should it be closed by a landslide. In 2020, a consultation exercise was carried out to consider 11 route corridor options to address issues at the Rest and Be Thankful route. More than 650 people provided feedback, and the Glen Croe corridor was chosen as the preferred route.
The Transport Scotland submission advises that
“timescales for completion of a long term solution to the issues at the Rest and Be Thankful range from 7–10 years”.
In the interim, Transport Scotland advises that work is progressing
“to look at a medium term resilient route through Glen Croe”
and that
“that work will seek to develop a finalised proposal by Autumn”
this year. The submission states:
“Since the A83 Taskforce was set up in 2012, meetings have been held every 6 months”
and that “a substantial project update” is due
“at the next Taskforce meeting in early 2022”.
A project-specific web page has also been launched on the Transport Scotland website.
Against that background, I am happy to invite comments from Rhoda Grant.