Thank you, convener, for the opportunity to appear before the committee. I know that HIAL appeared before the committee last week and covered a number of technical aspects of the project.
A key point that we need to remember when discussing this particular project is that it is about the continuation of air services in the medium to long term, which will help to secure the economic prosperity of remote and rural communities. The cessation of air services would have a devastating impact on those communities, and we have a responsibility to act now to ensure their continuation. Failure to do so would store up problems and risk connectivity and resilience.
HIAL has identified the risks that need to be addressed to ensure the continuation of services. As it set out last week, those include issues such as the need to improve resilience, staff recruitment and retention, the modernisation of working practices, the changing regulatory picture, which started under the European Space Agency and is likely to continue under the Civil Aviation Authority, and the opportunity to significantly improve on current safety levels.
This is not a new project; the issue first started in 2015. HIAL commissioned an independent study via the specialist consultancy Helios to advise on the best approach to addressing the issues that it faced. The decision to proceed was taken by the HIAL board in January 2018, and implementation of the project has continued since then. HIAL undertook extensive research in considering numerous options for how to address the issues that it faces, which included engagement with its staff and other stakeholders. That engagement will continue until the programme is completed, and HIAL has determined that the strategy that is being pursued is the one that addresses all the issues that it faces.
The consequence of the strategy is that a number of posts across HIAL airports will need to transfer to the new surveillance centre in Inverness. HIAL recognised from the outset that the project involves a significant change of process that needs to be carefully managed. That is why it has continued to engage with its staff and stakeholders to develop mitigations for the impacts that it will have on individual airports. Examples of that include commuting policy, which it is developing in consultation with the unions, and the recent announcement of the centre for excellence in Benbecula, which, if successful, could see staff from all over the Highlands and possibly from further afield training in Benbecula. HIAL will continue to explore all opportunities to mitigate the transferring of posts to Inverness and to support the economic development of the communities concerned.
I want to address some issues around the financing of the project, because it is important to distinguish between the budget that was agreed for the project and other cost figures that have been referenced at various points. I believe that there has been confusion in some quarters on that point. I am therefore providing clarity on those issues today.
There is only one approved budget for the project: the £48.4 million that was approved by Transport Scotland’s investment decision-making board in December 2019. That is made up of £34.7 million of capital budget, as referenced by HIAL in its appearance last week, and £13.7 million of revenue budget. The Helios report provided an initial proposal that evolved into the business case that was approved.
It is misleading to say that costs have increased between the initial proposal and the approved business case, as the two are not comparable. Although various figures have been reported in the media, the budget remains £48.4 million—as approved in December 2019—and it includes £6.8 million of contingency, which is normal for major infrastructure projects. As is the case with all projects, the scope of the project and the estimated costs of different elements have developed over time as more information has become available and options have been refined. As with any infrastructure project, costs will be carefully monitored through the ATMS programme board, the HIAL board and the independent audit programme with the Scottish Government.
We are still at an early stage, and the project is proceeding in line with its approved business case and its budget. I am more than happy to respond to any questions that committee members may have, convener.