Thank you, convener, and good morning. I am pleased to assist the committee with its scrutiny of our most recent six-monthly report on major capital projects. The projects have a positive impact on the places where we live, on how we travel and on the way in which many of our vital public services are delivered to communities across Scotland—not to mention the impact on our economy.
I will make a few opening comments. As the convener said, I am joined by a number of subject-matter experts from Transport Scotland, the Scottish Futures Trust and the Scottish Government, including the chief economist and colleagues from the health finance directorate and the infrastructure investment team. Should committee members have questions about projects or issues in those areas of knowledge, my colleagues and I will be very happy to respond. If there are questions about projects or programmes in sectors that are not represented by the panel, we will provide as much information as we can today and, of course, follow up in correspondence with more detailed points from the people who are directly accountable for the projects and programmes.
Today’s session takes place at a key time—a pivotal moment. We are nearing the end of the current 2015 infrastructure investment plan, so there is an opportunity to reflect on a range of investments that have been made. Much has been achieved over the past five years. About 90 per cent of the capital budget supports infrastructure, and net Scottish Government direct capital investment has totalled nearly £23 billion in the period from 2016-17 to the end of the 2020-21 financial year. As has been set out in previous infrastructure investment plan annual reports, that investment is estimated to have supported about 30,000 jobs.
A subset of such investment has, historically, been considered by the committee. The focus has been on major projects and certain programmes. Projects with a capital value of more than £20 million, alongside programmes with a capital value of more than £50 million, have been reported on every six months. Since 2016, 117 major projects, with a total capital value of £7 billion, have been completed. More will be reported as being complete in the next annual report, which is due at the end of this financial year. Our programme pipeline has led to major investment in delivery of superfast broadband, affordable housing, school buildings, expansion of early learning and childcare, and city region deals.
As was shown in the last six-monthly report, four major multiyear projects—the Aberdeen Baird family hospital and the Aberdeen north centre for haematology, oncology and radiotherapy, or ANCHOR, Her Majesty’s Prison Inverness, HMP Glasgow and the Dunfermline learning campus—will continue from this phase into the next parliamentary session, as parts of our new infrastructure investment plan. All four projects are fully funded in the future capital spending review and in the next infrastructure investment plan, which covers the five-year period from 2021-22 to 2025-26. Both were published on 4 February this year.
Similarly, major on-going programmes, including those relating to elective care facilities and to the A9 and A96, were intended to be delivered over a longer period than during the phase up to 2021. They are also set out in the next infrastructure and investment plan and are being funded through the capital spending review, so committee members can be assured of continuity.
All that allows me to draw attention briefly to some on-going improvements that we have sought to make in the information that is available to the committee for scrutiny. For example, since 2016 we have provided an overview of our annual infrastructure investment plan that is reported on each April. That strengthens the strategic information that is available to the committee, provides context for overall capital investment and shares much more information, as has been requested from time to time by members.
The next infrastructure investment plan up to 2025-26 covers all portfolios and synchronises all major investments over the five-year timeframe with a common vision and three key themes. Not only is there a plan for what the Government is choosing to invest in, but that ambition is matched with a funding package to ensure that it happens. That strengthens the strategic intent of the Scottish Government’s capital and infrastructure investment, which started with the national infrastructure mission that was announced in the programme for Government in September 2018.
The next infrastructure investment plan is larger than this one and includes a pipeline of £26 billion of itemised work within more than £33 billion of capital allocations. That is almost 50 per cent larger than was the case for the past five years, which has come through a combination of actions at the Scottish ministers’ hand, including deployment of physical framework powers, revenue-financed agreements, capital grants and financial transaction allocations. It is estimated that that will grow the “jobs supported” number to 45,000 and is a vital part of supporting Scotland through its recovery from the economic shock that has mirrored the public health shock of the coronavirus. Within that, £2 billion of new investment will focus on increasing—