Queensferry Crossing (Closure)

Topical Question Time

Tuesday 18 February 2020 Meeting of the Parliament Questions 20 contributions · 9 speakers Watch on Scottish Parliament TV

Speakers

Choose an MSP to read only their contributions

The record

20 contributions
Mark Ruskell Green Mid Scotland and Fife
link

To ask the Scottish Government what lessons have been learned from the recent closure of the Queensferry crossing. (S5T-02006)

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

Following the occurrence of falling ice in March 2019, Transport Scotland engaged with a range of expert advisers and undertook a review of worldwide experience of the issue. The review concluded that operational management remained appropriate and that arrangements should be made to enhance it by additional forecasting and monitoring. Acting on lessons learned, our engineers were monitoring the conditions on 10 February, which allowed them to act quickly when conditions worsened.

Initial learning from the events of 10 February has resulted in a five-point plan being put in place to further enhance monitoring and gather increased intelligence from the observations. A full debrief is due to take place on 24 February. A technical briefing will also be provided to Rural Economy and Connectivity Committee members and local MSPs to inform them of the circumstances of the closure, our developing understanding of why such events happen and how we plan to manage and respond to challenges ahead.

Visual monitoring, which remains the primary source of understanding the effects of such conditions, will be assisted by the installation of ice sensors in the coming months.

The design of the bridge was approved by Parliament in 2011.

Mark Ruskell Green Mid Scotland and Fife
link

The closure of the bridge came as a shock to many, not least to Fife Council, which last week informed me that it had no prior warning of the plan to close the bridge from either Transport Scotland or Amey; nor was it consulted on that action. Is a formal emergency closure procedure in place for the bridge? If so, who are the key stakeholders for the procedure? Was it implemented according to the plan, and why were local councils excluded from the process this time round?

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

I understand and recognise the difficulties that the bridge closure caused people, and I regret that, given that a very quick decision was made to close the bridge. As I am sure the member and others in the chamber will appreciate, the decision was taken for safety reasons. It was recommended by the operator, Amey, and supported by Police Scotland, which is why the action was taken to close the bridge within a short period of time.

From the discussions that I have had with the engineers who were involved in the decision, my understanding is that, because of the diversion works that needed to be put in place, they engaged or sought to engage with Fife Council in order to make it aware of the closure. They also contacted public transport providers to look at what enhanced public transport provision could be made. I therefore understand that attempts were made to make contact with Fife Council within the very limited period of time that was available between the decision to close the bridge and the diversion being put in place.

However, the debrief on 24 February that I mentioned, which will be conducted by the engineers and those managing the bridge, is an opportunity to look at further measures that can be put in place to improve communication when such instances occur again.

Mark Ruskell Green Mid Scotland and Fife
link

I welcome the fact that those matters can be considered at the debrief, and I hope that lessons can be learned. However, last Tuesday, I was also contacted by residents of Kincardine, whose village once again faced gridlock following the official advice from Transport Scotland for people to divert via the Kincardine and Clackmannanshire bridges. Given that the opening of the Queensferry crossing has resulted in more than a million extra vehicle journeys across the Forth, will the cabinet secretary accept that simply diverting traffic via Kincardine is no longer an option, and that emergency closure plans need to be developed that prioritise the modal shift to public transport first and foremost.

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

I very much recognise the concerns and challenges that have been created for residents who live on the diversion route, particularly in places such as Kincardine. When the decision to close the bridge was arrived at, action was taken to look at what enhanced public transport provision could be provided. For example, one of the carriageways on the Forth road bridge is presently undergoing major refurbishment work, but the other carriageway is operating as a contraflow for public transport provision. It was agreed with Stagecoach and other bus providers that there would be a 50 per cent increase in bus provision the following morning for people who were trying to make their way into Edinburgh and people trying to make their way from Edinburgh to Fife. Alongside that, ScotRail considered what enhanced morning peak-time services it could provide. Those services were enhanced and additional buses were provided to deal with overcrowding. As soon as the diversion had to be put in place, the first port of call was enhancing the public transport provision.

Given that major refurbishment work was taking place on the Forth road crossing, one of the actions that I have asked my officials to consider is minimising works on the crossing in future winter periods so that it can be used as a diversion route should that be required. That would reduce the need for the extended diversion route through places such as Kincardine.

Ken Macintosh The Presiding Officer · West Scotland
link

I inform the cabinet secretary and members that eight members wish to ask supplementary questions. We will try to get through as many as we can.

Murdo Fraser Con Mid Scotland and Fife
link

For my constituents in Fife, one of the most frustrating aspects of last week’s closure of the Queensferry crossing was the fact that—for entirely understandable reasons—they were not able to divert across the Forth road bridge. Given what the cabinet secretary has just said, in the event of a potential future closure of the Queensferry crossing, will consideration be given to allowing vehicles to access both carriageways on the Forth road bridge, thereby avoiding some of the congestion in west Fife villages to which Mark Ruskell referred?

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

Murdo Fraser makes a reasonable point. There is a challenge in striking a balance between continuing the public transport provision and using the Forth road bridge as a diversionary route for cars, and I have already asked my officials to explore that possibility. I am very keen to explore and understand the issue, but we have to recognise that that could cause significant congestion in areas such as South Queensferry, given that temporary road works would have to be put in place.

All those issues have to be worked through, and I have asked officials to ensure that that is done—including, as Murdo Fraser suggested, by identifying whether further measures could be put in place to manage the situation better.

Gordon MacDonald SNP Edinburgh Pentlands
link

I think that most motorists understand that safety has to be paramount and that the closure of the bridge was, indeed, due to exceptional weather conditions. Will the cabinet secretary outline what measures are in place to optimise information sharing with motorists? How can that be improved going forward?

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

As soon as the decision to close the bridge was made, a range of information was placed in the national media and across social media to inform people of the decision and its implications for them. That included information on the need to use the diversionary route, and on enhancement of public transport provision that was being made.

It is clearly important to ensure that, when such incidents occur, our communication of information is as timely and effective as possible. I am sure that all members recognise that, when a safety issue arises as it did last week, it is important that action is taken swiftly. There were attempts to communicate as effectively as possible, but I am always prepared to look at how we can enhance communication in the future. I will ensure that the points that Mr MacDonald and others have raised are taken forward in the debrief.

Colin Smyth Lab South Scotland
link

The issue was first identified last March, and the cabinet secretary advised the Rural Economy and Connectivity Committee in May that contractors had been

“appointed to monitor the issue, identify the exact source of it and look at what mitigation may have to be put in place”.—[Official Report, Rural Economy and Connectivity Committee, 15 May 2019; c 14.]

If work has been going on since the spring, what exactly have those mitigation measures achieved? Why was there not full mitigation in time for this winter?

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

A range of work has been undertaken. As I have mentioned, expert advisers have been engaged with, and advice has been taken worldwide on the particular problem and ways in which it can be more effectively addressed. A number of points that relate to enhancing the weather forecasting for the bridge and looking at the introduction of weather sensors and ice sensors have arisen from that. That work was all finalised last November. There has been a procurement exercise and the award of the contract is due to take place in the next couple of weeks, the plan being to install the sensors in the coming months.

All the expert and international advice is that human observation is the critical element in identifying whether there is any ice on the bridge’s structures. The incident that occurred last March involved an unspecified area of the bridge—at that time, the engineers were not able to identify where the ice had come from. The incident that occurred last week clearly involved the cables. That information will inform the approach that will now be taken with ice sensors and the installation of any other equipment that will be necessary to monitor the issue.

Mitigation measures could, however, be more complex, given that such icing occurs only in very specific circumstances. There was no problem with snow or ice accumulation on the Queensferry crossing during the beast from the east, and there have been no problems in other periods of adverse weather. The problem appears to occur only in very specific circumstances, which will make it more challenging to find a means of mitigation. However, that is part of the work that engineers will take forward in the weeks and months ahead.

Jamie Greene Con West Scotland
link

I welcome the new members of the Government’s front bench and thank the Cabinet Secretary for Transport, Infrastructure and Connectivity for the manner in which we have conducted our debates in the past few years.

The decision to close the bridge for safety reasons was the right one, but several vehicles were damaged prior to that decision being made. It is, frankly, a miracle that nobody was injured or worse. Winter is not over. Considering the severe consequences of falling ice, what reassurance can the cabinet secretary give to motorists who use the crossing that they can cross the bridge safely and without fear or risk to themselves or their vehicles during similarly inclement weather?

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

I am sorry if I am behind the news—I get the impression that Mr Greene is on the move to another portfolio. I have enjoyed my exchanges with him and I wish him well in his new portfolio.

There is a five-point plan in place, whereby enhanced monitoring will take place alongside additional forecasting. Following the incident last week, forecasters and engineers now have a clearer understanding of the perimeters within which this kind of icing takes place. They did not have that understanding following the incident that occurred last March. They can now more accurately predict when it is likely to happen and know when to undertake enhanced monitoring of the cables, which is where the ice fell from last week.

Those additional measures, which are over and above what was already in place prior to this winter, will be taken should the weather forecast indicate a risk that icing could occur. Once the sensory equipment is installed, it will provide an additional measure to support the engineers’ understanding. However, the primary source of information will be visual checks, which appear to be the core way in which such icing problems on any large structures of that type are identified throughout the world.

Alex Cole-Hamilton LD Edinburgh Western
link

I am grateful to the cabinet secretary for the extensive briefing that he offered Opposition parliamentarians last week.

It is now two years since the Queensferry crossing was given motorway designation, and the problem of icing is just one of a number of issues that have emerged during its operation. Those include problems with road layout at the bridge access and issues with traffic flow around South Queensferry. Those issues were meant to be swept up in the one-year review that was due to be published in December 2018, yet we are still waiting for the review. Can the cabinet secretary confirm when the review will finally be published?

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

The review has been delayed because of challenges with the data that were being used for the assessment work. I understand that Transport Scotland expects to receive that review in the spring of this year, when it will be technically reviewed. As soon as that technical review has been completed, the review will be published.

Liz Smith Con Mid Scotland and Fife
link

In his response to Murdo Fraser, the cabinet secretary said that his team will examine the various approaches to the Forth road bridge in situations in which there are difficulties. Can the cabinet secretary confirm whether that relates only to situations in which there are problems due to severe weather or whether that is a part of a general plan to review the approach roads in response to the issues that Alex Cole-Hamilton has just raised, which involve situations outwith times of bad weather? Can the cabinet secretary confirm that he is looking at those situations, too?

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

I can confirm that that is not the case. The work will be only for the purposes of events during which the Queensferry crossing is not available and cannot be used. It will look at only exceptional circumstances, not the routine circumstances that the member referred to.

Ken Macintosh The Presiding Officer · West Scotland
link

I apologise to Alexander Stewart, Dean Lockhart and Claire Baker, as we have not been able to get through all the supplementary questions.

Motions, questions and votes

Linked from this item of the Official Report
  1. Time for Reflection Time for reflection · 2
  2. Business Motion Business motions · 1
  3. Queensferry Crossing (Closure) Questions · 20
  4. Flooding (Support) Questions · 8
  5. Fife Ethylene Plant (Elevated Flaring) Questions · 11
  6. Social Prescribing Debate · 59
  7. Minister and Junior Minister Debate · 9
  8. Decision Time Decision time · 2
  9. Gaelic-medium Education (Western Isles) Members’ business · 12

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.