Haudagain Roundabout (Link Road Project)

Portfolio Question Time Transport, Infrastructure and Connectivity

Wednesday 15 January 2020 Meeting of the Parliament Questions 8 contributions · 4 speakers Watch on Scottish Parliament TV

Speakers

Choose an MSP to read only their contributions

The record

8 contributions
Maureen Watt SNP Aberdeen South and North Kincardine
link

To ask the Scottish Government whether it will provide an update on the £30 million link road project at the Haudagain roundabout in Aberdeen. (S5O-03995)

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

Construction work is well under way on the A92/A96 Haudagain improvement project, and the main works contractor has already made significant progress on critical earthworks and utility diversions. The project is expected to open in spring 2021, subject to unforeseen circumstances, such as exceptional adverse weather.

Maureen Watt SNP Aberdeen South and North Kincardine
link

I was disappointed, but not surprised, to see a North East Scotland member, Liam Kerr, trying to score political points in the local press about police incidents at the Haudagain roundabout. Mr Kerr and his Westminster colleague have this week been called out by local campaigners in Laurencekirk for trying to do likewise in respect of the flyover for which they have spent years campaigning. Does the cabinet secretary agree that instead of obsessing over petty point-scoring—[Interruption.]—the Tories should welcome the investment in north-east roads, including the Aberdeen western peripheral route, that the Scottish National Party Government continues to deliver?

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

The Scottish Government has already committed more than £800 million of investment in road infrastructure projects in the north-east of Scotland. We have seen that very substantial benefits are already being provided by the AWPR.

We will not stop there. As the member made reference to, the Haudagain junction work is moving on apace. We expect that project to continue to be developed, and we expect to see improvements to traffic flow and to journey times, once it is completed.

The draft orders have been published for the new grade-separated junction at Laurencekirk. They are now out for public consultation, so the local community has an opportunity to express its views on the proposed works at the site. There will be a significant level of investment in that part of the north-east.

That investment sits alongside our plans for dualling the A96 between Aberdeen and Inverness, which is, at £3 billion, a major infrastructure project to improve connectivity from the north-east of Scotland to Inverness.

While the Tories carp from the sidelines, we will get on with doing the day job.

Liam Kerr Con North East Scotland
link

The link road is a good scheme, and I can assure Maureen Watt that the accident statistics that I was asked to comment on were not of my making. The taxpayers will want to know the cost. At the start of the project, the Government said that it would be £14 million—

Christine Grahame SNP The Deputy Presiding Officer · Midlothian South, Tweeddale and Lauderdale
link

Briefly.

Liam Kerr Con North East Scotland
link

The cost was £18 million in 2016; in 2019, it was £30 million; and, last week, Transport Scotland said that it was £49.5 million. Will the cabinet secretary say here and now that it will not rise again?

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

I presume that Liam Kerr is referring to the Haudagain roundabout project. The cost of the Haudagain roundabout project is £49.5 million. That includes all the wider aspects of the project, including purchase of land, public utility diversions, advisory fees, preliminary work, geotechnical work and environmental surveys. That is the overall cost of the project.

It never comes as a surprise to me that the Tories want to talk down Scotland and improvements that are being made in Scotland, such as the one to which my colleague Maureen Watt referred.

Motions, questions and votes

Linked from this item of the Official Report
  1. Independent Prison Monitors Members’ business · 12
  2. Rural Economy Questions · 1
  3. Women in Agriculture Questions · 6
  4. Forestry (Renfrewshire South) Questions · 6
  5. Budget (Rural Economy) Questions · 7
  6. Forestry (Fire Hazard) Questions · 4
  7. FAME Diesel (Impact on Farmers) Questions · 4
  8. Meat Products (US Regulatory Standards) Questions · 6
  9. Borders Railway (Rolling Stock) Questions · 11
  10. Aberdeen Western Peripheral Route Questions · 8
  11. Haudagain Roundabout (Link Road Project) Questions · 8
  12. Bellfield Interchange Questions · 4
  13. Rail Services (South Scotland) Questions · 4
  14. Reaching 100 per cent Broadband Programme Questions · 4
  15. Road Infrastructure Projects (Environmental Issues) Questions · 4
  16. ScotRail Franchise (Potential Buyers) Questions · 4
  17. Secondary Education Debate · 118
  18. Business Motions Business motions · 2
  19. Parliamentary Bureau Motion Business motions · 6
  20. Decision Time Decision time · 12
  21. World Wetlands Day 2020 Members’ business · 13

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.