Gail Ross is right about the cost of dualling of the A9 between Perth and Inverness: at £3 billion, it is the biggest infrastructure project that has ever been undertaken in Scotland. It is due to be completed by 2025. The programme continues to be on target.
The first part of the road to be dualled—the section between Kincraig and Dalraddy—opened in September, and the construction contract for the second section to be dualled, between Luncarty and Birnam, was awarded on 21 September to Balfour Beatty, which is undertaking preparatory work on temporary access roads, access work areas and ground-works offices—the site offices—between now and early next year. That work sits alongside some design work that is being carried out.
The A9 project is being taken forward in eleven sections. The orders for eight of the other nine sections—in other words, about 95 per cent of the orders—have been issued, and the one that is outstanding relates to a section that is being taken forward under a co-production model with the local community in the Perthshire area. Once that process is complete, the draft orders will be issued for that section, too. As I said, the work is being phased, and 95 per cent of the draft orders for the dualling programme have been issued. We will just have to wait and see whether there are any public local inquiries into those orders.
As for the A96, the first PLI, dealing with the section from Inverness to Nairn, was completed last month. The reporter is finalising the representations that have been received in the course of the inquiry, and we will have to wait for the reporter’s submission to Scottish ministers on the matter.
We have also completed route options assessment work on the section between Hardmuir and Fochabers. The preferred route options were announced just yesterday, with a public exhibition taking place between today and Friday to allow local residents and interested parties to look at the detail.
The route options assessment work is also under way on the 26-mile section between east of Huntly and Aberdeen. Initial options are under consideration and, in October, there was a series of exhibitions at which people could provide feedback. The committee might be interested to note that, so far, 13,500 people have been engaged in the process of providing feedback on the proposed programme of work along the A96.