Tuesday 4 December 2018 Meeting of the Parliament Questions 28 contributions · 13 speakers Watch on Scottish Parliament TV

Speakers

Showing Michael Matheson only · show everyone

Michael Matheson’s contributions

13 contributions
Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

ScotRail’s performance is clearly not where it should be, and I raise that matter regularly—and I have done so recently—with Alex Hynes, who is the managing director of the ScotRail Alliance.

The level of cancellations that are being caused by the rest day working dispute is unacceptable, and I call on the National Union of Rail, Maritime and Transport Workers and ScotRail to resolve the dispute without further delay. The impact of ScotRail’s continued training of staff to deliver the coming timetable changes is equally unacceptable.

The planned changes will deliver the first phase of this Government’s programme to significantly improve services across much of the Scottish rail network through our record investment in infrastructure and rolling stock. It is very disappointing that passengers are bearing the brunt of the late arrival of the new trains and the knock-on impact on training schedules, and the situation is being exacerbated by the industrial dispute. I will be making that very point when I meet Mr Hynes later today.

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

I certainly recognise the concerns of the member’s constituents—my constituents have the same concerns—about the challenges, particularly over the past few days, as a result of a combination of the training programme for the new class 385 trains coming in and the on-going industrial dispute.

The member will be aware that significant investment has been made in providing new rolling stock, and new electric trains will enhance the services across many parts of the Scottish network. The new timetable comes into force as of 9 December, with the new rolling stock that is being provided by Hitachi. That will allow the remaining rolling stock to be cascaded to other parts of the network, including Fife. Alongside that, further improvements will be made to the timetabling next May, and the full programme will be completed by next December. That will increase the number of seats and the rolling stock available and improve the timetabling of services across the country.

I recognise passengers’ frustrations over the difficulties in recent days in particular. Our considerable investment in rolling stock and infrastructure will deliver improvements as we make the timetable changes, which start at the end of this week.

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

The ScotRail Alliance is in no doubt about my views on its performance to date; when I meet the ScotRail Alliance’s MD this afternoon, he will be in no doubt about my views on its performance in the past couple of days in particular.

I call on the RMT and ScotRail to get round the negotiating table and settle the matter sooner rather than later, to make sure that we put passengers first.

It should be recognised that the fare increase, which I know is unwelcome, is the lowest increase in the United Kingdom, because of the rail fare cap arrangements that we have in Scotland. Almost two thirds of the cost of the railway network in Scotland is met by the Scottish Government. That is more than any other part of the UK provides. The Scottish Government provides a considerable level of resource to minimise the fare increase, although I recognise that any increase is unwelcome.

All members can be assured that the ScotRail Alliance is in no doubt about my views on its performance to date; I will be making that point again to it this afternoon.

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

Mr Crawford has raised a number of factors. He will be aware that electrification of the line into his constituency has just been completed—the testing of the line was completed last week—for the introduction of the new 385 trains, which will improve the capacity and reliability of the service for his constituents.

The communication issues that Mr Crawford mentioned have been raised with ScotRail, and my officials and Transport Scotland will continue to raise them so that ScotRail improves its communication with the public.

I assure the member that we will continue to ensure that ScotRail and its partners are doing everything possible to improve the services that they offer to the travelling public. He can be assured that I will impress that on ScotRail when I meet it later this afternoon.

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

I will give signing the petition a miss, but I understand the concerns of the public, which the member described, about the removal of the kids go free promotion. That is a commercial product that it is in ScotRail’s hands to choose to implement; it has chosen to change its arrangements. ScotRail has said that more tickets will be available for children to travel for £1 under the new scheme than have been available under the kids go free promotion.

As I said in response to Murdo Fraser, we do a considerable amount to cap price increases in Scotland. Because of the considerable investment that the Scottish Government puts into ScotRail, the fare increase in Scotland is the lowest of any part of the UK.

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

I am more than happy to raise that question with Alex Hynes when we meet this afternoon. I emphasise that the new Hitachi 385 rolling stock that is coming in will increase capacity on the rail lines, which will allow more seats to be available on the Borders railway, particularly at peak times.

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

The timetabling matter, which Network Rail is taking forward, has been in process for the past two years and has involved a range of engagement across different parties and stakeholders.

As I said, the 385s are coming into service—some are in service, but additional ones are coming into service daily. The electrification of the line to Dunblane will allow the 385s to operate there, which will increase capacity to Dunblane. That will come into play with the timetable change on 9 December.

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

There is absolutely no doubt that ScotRail’s infrastructure has had a significant impact on its performance. Members have only to look at the figures for the most recent four-week period that has been recorded, which takes us up to 10 November, in which 59.5 per cent of delays on the ScotRail network related to Network Rail. That is unacceptably high.

I welcome the fact that, last week, the Office of Rail and Road decided to take action against Network Rail because of its poor performance and the impact that that is having on passenger services. There is no doubt in my mind that, in order to address such issues, we need to align more effectively the providers of both rolling stock and infrastructure. In Scotland, the best way of achieving that would be to devolve Network Rail so that it would be responsible and answerable to this Parliament.

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

Alexander Stewart will be aware that in order to ensure that we can deliver on the enhancements that will be brought about by the new timetable across the country, changes are being made in areas such as Dunblane; a key part of that is to improve the infrastructure in that area. That is why the line has been electrified up to Dunblane. That is a significant investment, which will allow the new Hitachi 385s to operate on that line, increase capacity and provide greater resilience there.

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

I am aware of concerns around the performance of the TransPennine service. Its public performance measure is at 71.65 per cent for the latest period, which was from 14 October until 10 November. That shows a marked deterioration over the past year. The concerns that Joan McAlpine has raised are a matter for the Secretary of State for Transport and the Department for Transport in London but, of course, I will pass them on. Some of my constituents have also raised concerns about the reliability of that service and its poor punctuality.

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

I have recognised that the level of service that is being provided at present is not acceptable and that ScotRail and Network Rail need to take action to address the issues. The Donovan review set out a range of measures that will help to improve resilience in the Fife area. The new rolling stock that is coming in will allow a cascade of other stock to go out to the Fife lines. For example, where there are four carriages at peak times at present, that will increase to six. It will also increase capacity at off-peak times. The ScotRail Alliance has also given an undertaking to review the existing timetable to see how it can improve it further in future.

However, I have no doubt that the level of performance that passengers on the Fife line have experienced is not to the acceptable standard, which is why action needs to be taken to address such issues.

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

I will ask ScotRail’s representatives to provide Jenny Gilruth with that information.

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

I am sure that the member recognises that people who work in the ScotRail and Network Rail organisations work very hard to provide the best service possible. I fully recognise that.

The incident to which the member referred is being investigated by the ORR, because it came about as a result of technical failings in the train. There are failsafe systems that should have prevented that from occurring. We must await the outcome of the ORR’s investigation into the matter.

Motions, questions and votes

Linked from this item of the Official Report
  1. Time for Reflection Time for reflection · 2
  2. ScotRail Performance Questions · 28
  3. Cairngorm Mountain Ltd Questions · 14
  4. Thyroid and Adrenal Testing, Diagnosis and Treatment Debate · 30
  5. Veterans Debate · 24
  6. Counter-Terrorism and Border Security Bill Bill debate · 10
  7. Point of Order Procedure · 2
  8. Decision Time Decision time · 8
  9. Autistic Children’s Experiences of School Members’ business · 37

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.