Yes please, convener. Once again, I thank the committee for the opportunity to provide an update on the major transport projects in my portfolio. Since my previous appearance before the committee, work has progressed at some pace on all the projects for which I am responsible, with significant progress being made across the projects.
First, I will comment on the Aberdeen western peripheral route Balmedie to Tipperty project. As I have previously advised, the AWPR, at 58km in length, is the longest new roads project that is currently under construction in the United Kingdom. It is the equivalent of building a completely new road between Edinburgh and Glasgow. When it is complete, it will provide substantial benefits across the north-east, boosting our economy, increasing business and tourism opportunities, improving safety and cutting congestion, as well as improving opportunities for public transport facilities.
In the statement that I made to Parliament on 22 March, I advised that, following consultation with Transport Scotland’s technical advisers, it would be prudent to anticipate a late autumn 2018 opening date. Although I fully appreciate the contractor’s continued ambition to target a summer 2018 opening, Transport Scotland’s technical advisers on site remain of the view that a late autumn 2018 opening may be more realistic.
I also confirmed at that time that we would continue to work with the contractor to identify whether any further sections of new road could be opened in advance of the whole project. I reassure the committee that, where that is possible without impacting on the timetable for completion of the overall project, we will endeavour to ensure that those sections of road are opened.
Works are progressing well. We saw the Balmedie and Blackdog junctions open at the end of April and the beginning of May respectively, and work is nearing completion on the River Dee crossing.
Elsewhere in the project, work is progressing well, and we are now at a stage where we can start to consider plans for a suitable event to mark the opening of this very significant project, which was first proposed, I think, 65 years ago. I look forward to being able to provide further information on the opening event in due course. Meanwhile, I take the opportunity to thank those who reside in the north-east for their continued patience while the essential works are being undertaken.
The A9 dualling programme continues to make significant strides forward with the news that the second section, between Luncarty and Pass of Birnam, is expected to be awarded in the summer. The contract for advanced tree-clearing works for the A9 Luncarty to Pass of Birnam project is expected to be awarded in early June, with works commencing on site soon afterwards. That will help to de-risk the main construction contracts, ensuring that this important seasonal work does not unnecessarily delay the overall construction programme.
Draft orders for five of the remaining dualling schemes were published recently, collectively representing 36 of the 80 miles to be dualled. It is expected that the draft orders for a further three dualling schemes will be published in the coming months. The dualling programme is one of the biggest transport infrastructure projects in Scotland’s history. We remain committed to completing the work by 2025 and we remain on target to meet that commitment.
Of course, that project is not just about the building of the road. My colleague the Cabinet Secretary for Finance and the Constitution, Derek Mackay, recently attended the launch of a tourism app that is being taken forward by Transport Scotland’s A9 dualling team as part of the Government’s innovative CivTech challenge, which looks to new technology businesses to solve technological challenges. The Highland discovery app has been developed to promote the less-visited rural heartlands of Scotland and will help tourists to navigate the many visitor attractions and facilities on and around the A9 corridor. The app focuses on small community facilities and businesses and includes an in-car audio channel offering Scottish stories and songs.
Design work continues on the A96 dualling Inverness to Aberdeen programme. The work that we are progressing includes a rolling programme of regular engagement with local communities and other stakeholders to ensure that locals, road users and businesses that are affected by the work are kept fully informed. More important, that will ensure that the vital feedback that we receive is taken into account as we develop our plans.
So far, 11,500 people have visited public engagement events on the A96 dualling. As part of that programme of engagement, between 27 February and 2 March, local communities and road users were able to view and comment on proposed changes to the options that are being developed for the 46km Hardmuir to Fochabers scheme. Nearly 1,400 people attended the drop-in sessions over four days, and the feedback that was received has been extremely important to the team as it continues the route options assessment process for that section of the A96 dualling. We are on target to identify a preferred route option later this year.
Building on the early meet the team public engagement events that were held in November 2017 on the 42km east of Huntly to Aberdeen scheme, which were attended by over 1,000 people, we expect to present the options under consideration to the local communities later in the year to allow them the opportunity to provide important feedback that will help to shape our preferred option, which we hope to identify in 2019. Along with our commitment to dual the A9 between Perth and Inverness by 2025, dualling the A96 will ensure that the road network between all of Scotland’s cities is of at least dual carriageway standard by 2030.
Since the M8 bundle project fully opened to traffic on 1 June, we have seen significant journey time savings across the central Scotland motorway network. Finishing works are on-going and are expected to be completed in the coming months.
The committee might be aware that part of the Lagan Construction Group went into administration on Monday 5 February. Lagan formed 20 per cent of the construction joint venture that was charged with delivery of that project on behalf of the Scottish Roads Partnership. Ferrovial Agroman is the other partner, and the contract makes it jointly and severally liable to the Scottish Roads Partnership in respect of its obligations and liabilities. The obligation is now on Ferrovial to deliver the outstanding construction works. Approximately 10 Lagan employees were working on the project at the time of administration. Five have moved on to new employment and five are being re-employed through the project. Lagan is not part of the Scottish Roads Partnership, which is the design, build, finance and operate company that is responsible for the on-going maintenance of the project for the next 30 years. The administration will therefore have no impact on the operation of the roads.
I will move on quickly to Prestwick airport. Since the Government purchased the airport in 2013, we have been clear that it must operate on a commercial basis at arm’s length from both the Scottish Government and ministers. That allows the senior management team at the airport the freedom to pursue the business opportunities that align with the strategic direction of the business. My view is that the airport is moving in the right direction. For instance, recent Civil Aviation Authority figures show that, in 2017, it recorded an increase in passenger numbers of over 3 per cent, to approximately 696,000, compared with the equivalent 2016 figures. Although that is a relatively modest increase, it clearly demonstrates a move in the right direction.
The airport performed well during the recent adverse weather. While conditions across the country were certainly challenging, Prestwick, as ever, remained open and operational throughout the period and it accepted a number of flight diversions from other airports, which are quite lucrative forms of business. I was pleased to hear that the committee has taken up the offer that I made for it to visit the airport, and I understand that that has been arranged for 4 June. That will give members a really good opportunity to tour the airport and hear at first hand about the improvements that have been made.
I thank the committee for the opportunity to update you today. I am happy to take any questions.